NESO projects £3.9bn grid constraint costs

NESO projects £3.9bn grid constraint costs

NESO forecasts £3.9bn in electricity thermal constraint costs during 2027. Transmission congestion, higher replacement generation costs, and planned network outages are expected to keep expenditure elevated ahead of major grid reinforcements.


IN Brief:

  • NESO forecasts £3.9bn of thermal transmission constraint costs in 2027, compared with £2bn recorded during 2025/26.
  • Planned network outages are expected to increase costs, with the 2027 projection estimated to be 16% lower without them.
  • The system operator has identified 26 initiatives, including dynamic line rating, improved outage planning, and demand flexibility.

National Energy System Operator (NESO) expects thermal constraints on Great Britain’s electricity transmission network to cost £3.9bn in 2027, reflecting persistent congestion, higher replacement generation costs, and the temporary reduction in network capacity required for reinforcement work.

The projection follows £2bn of thermal constraint expenditure during the 2025/26 financial year, when network restrictions accounted for approximately two-thirds of the electricity system’s total balancing costs. NESO expects these pressures to continue as renewable generating capacity expands ahead of major transmission upgrades.

Thermal constraints arise when the electricity that would otherwise flow between different regions exceeds the safe carrying capacity of the circuits connecting them. NESO must then adjust generation or demand to prevent the transmission system operating beyond its permitted limits.

These restrictions have become particularly significant between Scotland and England. Large quantities of wind generation are available in northern parts of Great Britain, while substantial electricity demand is concentrated further south, creating high power flows across several important transmission boundaries.

When available generation exceeds the capacity of those boundaries, some generating stations must reduce their output. NESO then arranges replacement electricity from other locations to ensure demand remains supplied while the affected circuits operate within their permitted ratings.

This redistribution of generation creates expenditure through the electricity balancing arrangements. Wind farms may be paid to reduce production, while other generators, frequently gas-fired power stations, are paid to increase output elsewhere on the network.

The cost of replacement electricity accounts for a substantial proportion of the total. NESO’s analysis indicates that approximately 75% of thermal constraint expenditure during 2025/26 was associated with replacement energy, predominantly supplied by gas-fired generating units.

Higher gas prices have therefore increased the cost of managing congestion. The operator recorded rising average costs for balancing mechanism actions during 2026, with the average price increasing from approximately £90/MWh in April to £126/MWh in September.

The trend continued into October, when balancing expenditure reached record levels. These increases reflect both the quantity of electricity that must be redispatched and the price of the replacement generation required to maintain supply.

During 2025/26, total electricity balancing costs reached £3.1bn, an increase of 16% on the previous year. Payments to wind farms to reduce generation amounted to less than £500m, considerably below the total thermal constraint expenditure.

That distinction is important when interpreting the costs of network congestion. The payments associated with reducing renewable generation are only one part of the balancing process, while securing electricity from alternative sources can account for most of the expenditure.

NESO estimates that approximately 13% of Great Britain’s available wind generation was curtailed because of constraints during 2025/26. The proportion was considerably higher for generating capacity located north of the B6 transmission boundary.

The resulting expenditure reflects the interaction between generation locations, network carrying capacity, and available alternatives. Electricity that cannot be transported across a constrained boundary must be replaced by resources capable of supplying demand on the other side.

Transmission reinforcement is intended to increase the amount of electricity that can move between regions, but construction introduces its own operating restrictions. Existing circuits frequently have to be removed from service temporarily so that equipment can be installed, modified, tested, or connected safely.

These planned outages reduce the transmission capacity available during the works, potentially requiring additional redispatch even though the completed infrastructure is intended to increase network capacity.

NESO estimates that thermal constraint costs in 2027 would be approximately 16% lower if the network outages included in its forecast were absent. This is a modelled comparison, not a separate category of expenditure already incurred.

The assessment highlights the importance of construction sequencing and outage coordination. Work on transmission assets must accommodate electrical isolation requirements, equipment availability, and the operating needs of the wider network, while maintaining sufficient capacity to meet demand.

The effect was apparent during 2025. NESO compared October and December, which experienced broadly similar market and wind conditions but different network availability. The operator found that October balancing costs were approximately 34% higher, with lower available capacity across important Scottish transmission boundaries contributing to the difference.

Accelerating major network reinforcement remains NESO’s principal structural response to rising constraints. New transmission capacity should allow more electricity to reach demand centres without redispatch, although the associated construction and commissioning programmes will take several years to complete.

The operator’s longer-term projections remain highly sensitive to the rate at which generation and network infrastructure are developed. In its net zero pathways, thermal constraint costs could reach between £6.8bn and £7.7bn in 2030 if clean generation expands broadly in line with national ambitions while planned transmission reinforcement is not accelerated.

A separate scenario involving slower energy system development produces lower projected costs of approximately £4.2bn in 2030. That outcome also assumes lower gas and carbon prices, demonstrating that the difference between scenarios cannot be attributed to the volume of renewable generation alone.

NESO expects constraint costs to fall significantly in the early 2030s as major transmission projects enter service. The exact timing and extent of the reduction will depend on network delivery, generation deployment, electricity demand, fuel prices, and operating conditions.

Alongside network construction, NESO has identified 26 initiatives spanning strategic planning, electricity markets, network utilisation, and system operation. These measures are being developed with government, transmission owners, and other electricity industry organisations.

Dynamic line rating is among the measures intended to increase the usable capacity of existing infrastructure. Conventional conductor ratings are commonly established using assumptions about the environmental conditions under which an overhead line must operate safely.

The thermal capacity of an overhead conductor depends on the relationship between electrical heating and heat loss to the surrounding environment. Wind speed, ambient temperature, and solar radiation affect conductor temperature and therefore influence the current that can be carried within the permitted limits.

Dynamic ratings use more closely observed or forecast operating conditions to establish the capacity available at a particular time. Under favourable conditions, this can allow additional electricity to flow through an existing circuit without immediate conductor replacement.

NESO estimates that expanding dynamic line rating could save approximately £800m to £1bn between 2026 and 2030. The calculation is based on modelled improvements in network capability, with the final benefit dependent on installation, operational implementation, and actual system conditions.

Constraint intertrip services provide another means of increasing usable network capacity. These arrangements allow specified generating units to be disconnected automatically following particular network faults, supporting secure operation while reducing the need for more extensive restrictions before a fault occurs.

The approach requires reliable protection and communication arrangements, together with suitable contractual agreements. Its application depends on the characteristics of the relevant transmission boundary and the equipment participating in the service.

Demand flexibility could also reduce the volume or cost of redispatch. Electricity consumers capable of adjusting their consumption may be able to increase demand in areas with surplus generation or reduce it where network restrictions make additional supply more expensive.

NESO is developing these opportunities through services including Demand for Constraints and new constraint management markets. Their effectiveness will depend on the location of participating assets, response capability, commercial incentives, and the operating requirements of the electricity network.

More coordinated planning is expected through the Strategic Spatial Energy Plan and Centralised Strategic Network Plan. These programmes are intended to align future generation, demand, and transmission infrastructure more closely, reducing the risk of additional capacity being developed where the network cannot accommodate its output.

Operational measures can improve the utilisation of existing assets, but their savings remain dependent on the physical capabilities of the transmission system. New circuits, substations, and reinforcement schemes will still be required to accommodate substantial increases in electricity transfer between regions.

NESO’s £3.9bn estimate remains a forecast, with future expenditure dependent on network outages, gas prices, renewable generation, and the availability of replacement electricity. The operator expects to undertake further analysis with Ofgem as updated information on generation connections and transmission delivery becomes available.

The immediate programme combines operational improvements with longer-term construction. Dynamic line rating, intertrip services, outage optimisation, and flexibility arrangements may reduce expenditure before new transmission capacity enters service, while the delivery of major reinforcement projects will determine the extent of the longer-term reduction in constraints.


  • Oklo secures Centrus HALEU for Aurora deployment

    Oklo secures Centrus HALEU for Aurora deployment

    Oklo has signed definitive agreements for advanced nuclear fuel supply. Centrus will deliver HALEU from 2029 to support up to five Aurora powerhouses, with prepayments contributing to the expansion of US uranium enrichment capacity.


  • Shokeir consortium closes 900MW Egyptian wind financing

    Shokeir consortium closes 900MW Egyptian wind financing

    Shokeir Wind Energy has closed financing for Egypt’s 900MW project. The 86-turbine Gulf of Suez 3 development is preparing for phased commissioning from January 2028, with Orascom Construction responsible for the electrical balance of plant.