WIRSOL is developing new solar and battery infrastructure near Göttingen. The Parensen project comprises 39 photovoltaic systems and approximately 15MWh of battery capacity, with staged commissioning scheduled into 2027.
LION Smart has secured three German battery energy storage contracts. The 30MWh total covers an existing solar site, new solar development and standalone battery project, with grid connection targeted for early 2027.
R.Power has completed main equipment placement at Poland’s Jedwabno site. All 64 battery containers and 32 transformer stations are placed, but electrical commissioning and grid energisation remain outstanding.
HELLENiQ has brought its Thessaloniki battery storage installation into operation. The facility has 100MW of installed power and 200MWh of storage, while a separate 50MW/200MWh project at Florina remains under construction.
Two Gennaker offshore substations have departed their Dutch construction yards. The platforms form part of the 927MW OST-6-1 grid connection, with each platform described as approximately 450MW.
HEXA has detailed its planned Oyabe grid battery in Japan. The 50MWac/200MWh facility in Toyama Prefecture is targeting operation in May 2028, with Shirokuma Power appointed for engineering and construction.
Doral has completed construction of three Mammoth Solar expansion phases. The additional 900MWac is nearing commercial operation and will join the existing 400MW Mammoth North facility in Indiana, raising the complex to approximately 1.3GWac.
Enerven has secured the contract for Queensland’s Teebar battery project. Its delivery scope includes a 275/33kV substation and new high voltage connection, while Valo will supply the storage equipment for the 400MW/1,600MWh development.
Hams Hall’s two supergrid transformers were energised in September 2026. The two 220MVA units form part of the 350MW battery development’s 400kV grid connection, ahead of its planned commercial operation.
Endurance Motive has disclosed a battery integration contract in Spain. The €1.02m agreement covers two storage containers, installation integration and commissioning, with delivery planned for January 2027.