IN Brief:
- Rezolv Energy has appointed seven companies to construct the 1.36GWp Dama Solar development in western Romania.
- Three EPC contractors, two high-voltage infrastructure partners, and two module suppliers will deliver the principal construction packages.
- The project has secured up to €561m in financing and is targeting commercial operation in the second half of 2028.
Rezolv Energy has appointed seven contractors and equipment suppliers to construct its 1.36GWp Dama Solar development in western Romania, establishing the principal engineering, electrical infrastructure, and photovoltaic module supply arrangements for the project.
The appointments divide construction between three engineering, procurement and construction (EPC) contractors, two high-voltage electrical infrastructure partners, and two photovoltaic module manufacturers. Dama Solar is being developed in Arad County, with commercial operation targeted for the second half of 2028.
CHINT Green Energy, CMC Europe, and Solarpro will undertake separate EPC packages. EnergoBit and Siemens Energy have been selected to deliver the high-voltage electrical infrastructure, while Tongwei and Astronergy will supply the photovoltaic modules.
The contracts advance a development that secured financing of up to €561m in September 2026. Rezolv’s project subsidiary, West Power Investments, arranged the funding with a consortium of 14 lenders, supported by an anchor investment from the European Investment Bank.
Dama Solar will occupy more than 1,000 hectares and is expected to generate approximately 1,800GWh of electricity annually once operational. The output would be equivalent to around 36% of Romania’s total solar generation in 2025, based on national generation data from Ember.
The project’s scale requires the contractors to coordinate the installation of generating equipment with the infrastructure needed to collect, convert, and export electricity. The allocation of separate EPC and high-voltage packages establishes distinct responsibilities while retaining the requirement for integrated electrical design and construction sequencing.
Photovoltaic modules produce direct-current electricity, which must be converted into alternating current before delivery to the electricity network. The resulting output is collected through electrical circuits connecting groups of generating equipment to the plant’s wider distribution and export infrastructure.
The electrical design must accommodate the output characteristics of the photovoltaic arrays, the ratings of the conversion equipment, and the requirements imposed at the grid connection. Transformers, cables, switchgear, protection systems, and control equipment must operate together across a development extending over a substantial geographical area.
Dividing the site between three EPC contractors allows different construction areas and equipment packages to progress under separate delivery arrangements. However, the electrical systems cannot be treated as independent installations once the plant is connected to the wider network.
Interfaces between contractor packages must be coordinated to maintain consistent design requirements, equipment compatibility, and commissioning procedures. Variations in cable arrangements, protection settings, or control interfaces could otherwise complicate the integration of completed construction sections.
The appointment of EnergoBit and Siemens Energy establishes specialist responsibility for the high-voltage infrastructure. Rezolv has not disclosed the individual equipment packages allocated to each company, nor has it published the final substation configuration, transformer ratings, or export connection design.
Those specifications will determine how electricity produced across the solar park is transferred into the receiving transmission or distribution network. The high-voltage systems must accommodate the generating plant’s permitted export capacity while meeting requirements for voltage control, protection, metering, and operational communication.
Tongwei and Astronergy will supply the photovoltaic modules. Astronergy has identified its ASTRO N7 Pro technology as part of its involvement, although the final distribution of module quantities between the two suppliers has not been established in Rezolv’s announcement.
Module selection influences several elements of plant design, including the electrical configuration of the arrays, string voltage, current ratings, mounting arrangements, and the relationship between direct-current generating capacity and inverter capacity.
The 1.36GWp figure represents the combined peak direct-current rating of the photovoltaic installation under standard test conditions. It does not establish the maximum alternating-current output that can be exported to the grid, which depends on the conversion system and connection arrangements.
Annual generation will also vary with solar irradiance, temperature, equipment availability, and electrical losses. Rezolv’s 1,800GWh production estimate provides a basis for assessing the anticipated scale of the completed development but remains a forecast until the plant enters operation.
Construction is expected to employ approximately 1,500 people at peak activity. The simultaneous presence of multiple EPC contractors and specialist electrical suppliers will require coordination of site access, component delivery, civil construction, electrical installation, and successive commissioning activities.
The programme must also account for the movement of large quantities of photovoltaic modules, mounting equipment, cables, and power conversion components across the site. Storage and handling conditions, installation sequencing, and the availability of completed electrical infrastructure will influence how efficiently the individual construction packages can progress.
Dama Solar has secured two contracts for difference through Romania’s second renewable energy allocation round, held in August 2025. Together, they cover 520MW of the planned development, providing a commercial support mechanism for part of its generating capacity.
Rezolv has also signed a ten-year virtual power purchase agreement with Ahold Delhaize, covering electricity associated with Dama Solar and the separate Dunarea East wind project in Romania. The agreement adds a corporate offtake arrangement alongside the project’s existing financial support.
These arrangements provide commercial foundations for the development, although the construction and grid connection programmes remain essential before electricity can be generated and delivered. The financial close and contractor appointments represent separate project milestones, each addressing a different part of the delivery process.
Rezolv has allocated 82 hectares within the site for nature restoration rather than photovoltaic generation. The reserved area will need to be accommodated within the wider construction and operating arrangements, including permanent access and infrastructure corridors.
Dama Solar forms part of Rezolv’s approximately 2.8GW portfolio of large renewable energy projects in Romania and Bulgaria. Its construction will involve one of the largest coordinated photovoltaic installation programmes currently planned in the European Union.
With the principal contractors selected, the next milestones will involve progress across the EPC work areas, delivery and installation of high-voltage equipment, and completion of the electrical connections required for commissioning. Rezolv continues to target commercial operation during the second half of 2028.



