SSEN Distribution submits £8.7bn network investment plan

SSEN Distribution submits £8.7bn network investment plan

SSEN Distribution has submitted major electricity investment plans to Ofgem. Of that sum, £1.3bn is already approved and £7.4bn awaits determination. The plan targets 24% more capacity and 13.4GW of flexibility.


IN Brief:

  • SSEN Distribution has proposed an £8.7bn ED3 programme for 2028–33, comprising £1.3bn already approved and £7.4bn still subject to determination, plus a potential £1.5bn through uncertainty mechanisms.
  • The plan targets 24% more network capacity, 13.4GW of flexibility, and approximately 600km of overhead-line and cable resilience improvements.
  • Ofgem will determine the allowed investment and revenues, while the company proposes to keep household distribution charges flat in real terms until 2030 subject to approval.

SSEN Distribution has submitted an £8.7bn electricity distribution investment programme for the ED3 price control, covering April 2028 to March 2033. Ofgem has already approved £1.3bn of the proposed expenditure, leaving £7.4bn of the baseline plan for determination through the current process. The distributor, which operates networks in northern Scotland and central southern England, has identified a further £1.5bn that could be incurred through uncertainty mechanisms if needs and costs are established during ED3. That contingent amount would take potential total expenditure to £10.2bn; it is not part of the approved baseline.

The five-year plan proposes increasing network capacity by 24% through a combination of reinforcement and flexible operation. SSEN calls this its ‘build and flex’ approach: existing circuits and substations would accommodate more demand where thermal ratings, voltage limits and security standards permit, while physical equipment would be upgraded when the forecast load cannot be managed reliably by other means. Distribution reinforcement has long design, procurement and outage-planning cycles, whereas flexibility can be contracted for particular intervals. The choice depends on the anticipated duration of a constraint, the cost of available responses and whether enough capacity is electrically located where the problem occurs.

SSEN proposes using 13.4GW of flexibility through ED3, around six times the level in its current price control, rather than treating that figure as new installed generation. A battery could alter its charge or discharge schedule, an industrial customer could temporarily reduce demand, or another controllable resource could vary its output when a local constraint arises. A service procured for a short interval cannot necessarily cover sustained growth in peak loading, and its usefulness depends on the provider’s availability, response time and position on the network. The projected 13.4GW therefore describes the scale of flexibility the company wants to deploy across the period, not continuous power guaranteed to every customer.

The company also proposes offering 5GW of early-access electricity connections. Earlier access may allow a customer to energise equipment before every planned upstream reinforcement is complete, provided the connection operates within agreed limits and does not compromise system security. The detailed arrangements can involve restrictions on export or import during network constraints, depending on the connection and the relevant engineering study. SSEN has not identified every project that would receive early access, and a proposed connection pathway should not be confused with an unconditional right to draw the full requested capacity at all times.

Weather resilience work would include rebuilding or placing underground approximately 350km of high-risk overhead lines and replacing a further 250km of cables assessed as vulnerable to climatic conditions. Overhead circuits face wind, tree contact and other external damage, while buried cables may suffer failures linked to water ingress, insulation condition, joints or thermal loading. Undergrounding can reduce some exposure while complicating access for repairs and raising installation costs. Selecting a route and design requires examination of fault history, the surrounding environment, available diversionary feeds and the practicalities of carrying out work on an operating network.

The distributor is targeting 99.98% overall network reliability while halving the number of customers experiencing unusually frequent power cuts. These are proposed performance outcomes rather than improvements already achieved. Replacing vulnerable infrastructure can reduce exposure to repeated faults, but reliability also depends on protection coordination, fault location, switching capability and the speed at which crews can restore power when equipment is damaged. Network automation and asset monitoring can shorten the interval between a fault being detected and customers being supplied from an alternative route, where network topology makes that possible.

SSEN’s submission also calls for approximately 1,500 additional full-time equivalent skilled roles during ED3 and a 10% increase in spending with UK-based manufacturers by April 2033. The workforce requirement reflects the amount of planning, installation, testing and commissioning needed to deliver a larger programme without compromising live-network operations. Switchgear, transformers, conductors and protection equipment have different manufacturing and certification lead times, so suppliers must translate a five-year investment proposal into capacity plans long before individual assets are installed. SSEN estimates the domestic procurement objective could generate an additional £157m of spend.

For domestic customers, SSEN is proposing to keep the distribution component of electricity charges flat in real terms until 2030, subject to Ofgem’s determination and government support. The company envisages different mechanisms in its two licence areas: a shift in the timing of revenue recovery in central southern England, and a possible adjustment to the Hydro Benefit Replacement Scheme for northern Scotland at its 2028 review. Neither proposal fixes the total electricity bill, which also includes energy, transmission and other charges. The submission additionally proposes 10,000 more home battery packs for customers needing power-cut support, building on 20,000 being provided under ED2.

Ofgem will test the proposed spending, demand forecasts, service commitments and uncertainty mechanisms before setting ED3 allowed revenues. Draft determinations are expected in summer 2027, with a final decision towards the end of that year, ahead of the price control starting on 1 April 2028. The distinction between the £1.3bn already approved and the £7.4bn still under review will remain important as engineering suppliers assess likely order volumes. The eventual scope of reinforcement, resilience upgrades and flexibility procurement will depend on the regulator’s decision and subsequent network requirements.


  • First Inch Cape turbine components leave Dundee

    First Inch Cape turbine components leave Dundee

    Inch Cape turbine components have departed Dundee for offshore installation. Cadeler’s Wind Mover is transporting the first shipment for a planned 72-turbine, approximately 1.1 GW development, with installation and electrical commissioning still ahead.


  • Muir Mhòr floating wind farm wins conditional consent

    Muir Mhòr floating wind farm wins conditional consent

    Scottish ministers have consented the proposed Muir Mhòr floating project. The approval allows up to 1 GW of generation and associated offshore transmission infrastructure, subject to conditions concerning fishing activity and seabird compensation.