Power On secures Siemens Energy grid connection

Power On secures Siemens Energy grid connection

Power On has secured Siemens Energy’s Corby electricity connection contract. The 2.6 MVA connection will use an existing GTC primary substation, bringing forward the anticipated availability of power from 2029 to May 2027.


IN Brief:

  • Existing network constraints meant Siemens Energy's original connection would require reinforcement works.
  • Power On has identified available capacity at a primary substation serving a nearby residential development.
  • The alternative connection avoids a potential cable route extending more than 3.5 km through Corby.

Power On has secured a contract to deliver a 2.6 MVA electricity connection for Siemens Energy’s new facilities in Corby, Northamptonshire, using an existing primary substation operated by its sister company, GTC. The independent connection provider is targeting operation by May 2027, at least 18 months before the capacity would otherwise become available under the original network reinforcement timetable.

Constraints on the existing distribution network meant National Grid could not make the required capacity available until 2029 without pursuing an alternative connection. One option involved connecting to a circuit more than 3.5 km away, requiring excavation through central Corby and beneath a private railway line. The additional construction requirements would have increased the cost and duration of delivering the electricity supply.

Power On instead identified available capacity at a GTC primary substation serving a large residential development on the outskirts of Corby. Its proximity to the industrial estate provides an opportunity to connect Siemens Energy’s facilities without undertaking the more extensive cable installation programme or waiting for the original network reinforcement works.

The solution demonstrates the importance of assessing available electrical capacity across different infrastructure ownership arrangements. Power On and GTC both form part of BUUK Infrastructure Group, with the former providing connection design and construction services and the latter operating utility networks.

Power On is accredited under the National Electricity Registration Scheme as an independent connection provider, with independent distribution network ownership capabilities available through its wider corporate group. These arrangements allow it to consider connection opportunities extending beyond infrastructure operated directly by the incumbent regional distribution network operator.

The Corby development also illustrates how constraints affecting one part of a distribution network do not necessarily establish that equivalent constraints exist across an entire geographical area. Available capacity depends on the configuration and electrical loading of individual substations and circuits, together with the characteristics of the infrastructure through which electricity is transferred into the local network.

A primary substation serving residential development can have a demand profile that differs considerably from that of an industrial estate. Assessing whether additional commercial or industrial loads can be accommodated requires consideration of the timing and magnitude of existing demand, prospective customer requirements, transformer ratings, and the capacity of the upstream electrical infrastructure. Power On has confirmed that the GTC substation can provide the required supply, although detailed network assessment results have not been published.

The connection’s 2.6 MVA rating describes apparent power rather than the maximum active power that Siemens Energy can consume. The relationship between the two depends on the power factor of the connected equipment. Industrial installations incorporating motors, transformers, and power electronic equipment can impose different electrical loading characteristics from residential developments, making accurate load information important during connection design.

Connecting additional demand to an existing primary substation also requires assessment of the circuits serving the new customer. Cable ratings, voltage performance, fault levels, and protection coordination must remain compatible with the operation of the wider network. The availability of capacity at the substation provides the basis for the connection, but the electrical infrastructure linking it to Siemens Energy’s facilities must still be designed, constructed, and commissioned.

The alternative route avoids some of the civil engineering challenges associated with the more distant circuit. Installing electricity cables through developed urban areas can require coordination with highways authorities, existing utility operators, landowners, and infrastructure owners. Railway crossings introduce further requirements associated with access, engineering approval, and construction methods, potentially extending the period between connection design and energisation.

Earlier this month, National Grid began examining shared connection arrangements for industrial developments, reflecting the growing importance of identifying alternative approaches to providing electrical capacity. The Corby project addresses a different set of circumstances, using available infrastructure within an established independent distribution network.

For industrial developers, the timing of electricity availability can determine when production equipment can be commissioned and a completed facility brought into operation. Identifying suitable connection opportunities early in the development process can help align building construction, machinery installation, and electrical infrastructure delivery.

Power On’s May 2027 target brings the anticipated connection date substantially closer to Siemens Energy’s development timetable. The project will now progress through the engineering, construction, and commissioning activities required to make the 2.6 MVA supply available from GTC’s existing substation.


  • Power On secures Siemens Energy grid connection

    Power On secures Siemens Energy grid connection

    Power On has secured Siemens Energy’s Corby electricity connection contract. The 2.6 MVA connection will use an existing GTC primary substation, bringing forward the anticipated availability of power from 2029 to May 2027.


  • NeuConnect begins German interconnector cable landing works

    NeuConnect begins German interconnector cable landing works

    NeuConnect has begun installing nearshore electricity cables in northern Germany. Prysmian is delivering a 30 km installation programme at Wilhelmshaven, advancing construction of the £2.4 billion interconnector between Britain and Germany.