IN Brief:
- National Grid Electricity Distribution is partnering with regional authorities and Black Country Industrial Cluster on a multi-year programme for industrial electricity access.
- The first Network Innovation Allowance-funded project in Cradley Heath will assess ways to share the costs of accommodating additional industrial demand.
- The partners will also examine flexible connections, batteries, shared local generation and constrained-capacity solutions in Worcester and other manufacturing clusters.
National Grid Electricity Distribution has formed a regional partnership to test alternative electricity connection arrangements for manufacturers in the West Midlands, beginning with a project examining how groups of industrial customers could share the costs of accommodating additional demand. The programme was confirmed on 16 November and involves public authorities and the Black Country Industrial Cluster.
The partners are West Midlands Combined Authority, Worcestershire County Council and Black Country Industrial Cluster, working alongside the electricity distribution operator. The multi-year programme will work directly with manufacturers to assess constrained network capacity, flexible access, battery storage and local generation. Its first deliverables are technical and commercial proposals that can be tested against real connection needs.
Cradley Heath is the focus of the first project. Industrial operators in the area will examine a model in which the costs associated with connecting additional electricity demand can be shared across businesses instead of being assessed as wholly separate investments. Network Innovation Allowance funding supports the Cradley Heath work, which will use forecast industrial demand to examine the costs and practical arrangements for connecting additional load. National Grid has not specified a project budget or capacity figure.
A factory increasing its electrical demand can trigger reinforcement beyond its own switchroom. Transformers, feeder circuits, switchgear and upstream network assets may face thermal-loading or fault-level limits, with the final work determined by existing agreements and local operating conditions. Shared planning could allow nearby factories to evaluate network upgrades against their combined demand profiles instead of progressing entirely separate connection proposals.
Where several manufacturers operate close to one another, their individual maximum demand does not necessarily occur at the same moment. A shared assessment can examine coincident peaks, available headroom and opportunities to distribute investment in additional network capacity. Any arrangement still has to respect individual connection limits, protection settings, operating standards and the commercial rights of participating customers.
The Cradley Heath work will use forecasts of industrial growth and electricity demand to test possible arrangements. Underestimating load can leave reinforcement undersized when new equipment arrives; assuming every factory reaches maximum demand simultaneously can inflate the scale of required works. The assessment will need realistic operating profiles as well as equipment ratings.
National Grid says the new programme follows a West Midlands Industrial Dialogue that brought together more than 50 businesses and identified 30 possible solutions to connection and electricity access problems. The 30 proposals included shared connections, flexible agreements, batteries, microgrids and greater use of locally generated electricity. The new programme is intended to develop and test options arising from that dialogue.
The region has a concentration of energy-intensive manufacturers using electrical loads such as furnaces, ovens, kilns and process equipment. Converting an industrial process from combustion to electricity can change its maximum demand, hours of operation and sensitivity to interruptions. A connection designed around an existing production process may therefore require substantial work before a factory can add electrical heating or expand a line, even where its annual energy consumption changes less dramatically.
Flexible connections could allow a participating factory to reduce imports during defined periods of network stress while making greater use of available headroom at other times. The engineering feasibility depends on the process: some plant can defer a batch or shift an auxiliary load, while equipment that must run continuously may require storage or another source of reliable power before it can accommodate restricted imports.
On-site generation and batteries can alter the electrical demand a distribution operator sees at a connection point, although their contribution depends on power rating, energy capacity and state of charge. A battery capable of reducing a short demand peak does not provide unlimited capacity through an extended production shift. Similarly, a local generator may reduce imported electricity during certain hours but requires appropriate protection, control and export arrangements if it operates alongside the public network.
The partners also plan to explore industrial areas in Worcester, including Warndon, which National Grid identifies as a strategic development area recognised by the National Energy System Operator. Warndon has already completed an industrial decarbonisation assessment. Other industrial clusters may subsequently be selected to test whether approaches designed around specific local constraints can be adapted to different demand patterns and network conditions.
The programme will bring the distributor, manufacturers and public authorities together while connection and investment plans are still being developed. Sharing reinforcement costs requires an agreed method for allocating expenditure, managing changes in demand and protecting the reliability of each participating connection. Those commercial arrangements will have to be tested alongside the engineering options.
Alongside the initial Network Innovation Allowance-backed work, National Grid and Black Country Industrial Cluster intend to seek support from the Strategic Innovation Fund for further testing with industry. That application would support further evaluation, subject to an award. Wider use of the approaches will depend on technical feasibility, customer participation and the way shared connections are treated under network regulation.
Manufacturers will now help identify the highest-priority connection constraints, beginning in Cradley Heath before further work in Worcester and other clusters. The first assessments will establish whether grouped demand, flexible imports and shared reinforcement expenditure offer workable alternatives to conventional individual connections. Construction decisions and any resulting increase in available capacity will follow those technical and commercial tests.