IN Brief:
- The transport exercise used the operational cask without radioactive fuel inside it.
- Finland granted Posiva an operating licence extending until the end of 2070 on 22 October.
- Posiva expects to dispose of approximately 30 to 40 canisters annually during its initial operating period.
Posiva has completed a further transport exercise at its spent nuclear fuel encapsulation plant in Olkiluoto, Finland, using the transfer cask intended for operational service. The test advances preparations for the commencement of final disposal activities following the Finnish government’s decision in October to grant the company an operating licence.
The exercise differed from earlier trials in which Posiva used equipment designated specifically for testing. The latest transport involved the actual transfer cask intended for use during future operations, although it did not contain radioactive fuel. Successful completion allowed personnel to gain further experience with the equipment before the facility begins receiving spent fuel.
Posiva is responsible for the final disposal of spent nuclear fuel from Teollisuuden Voima’s Olkiluoto nuclear power station and Fortum’s Loviisa facility. Its development comprises the encapsulation plant and the ONKALO geological repository, establishing the infrastructure through which fuel from the two generating stations will ultimately be placed into permanent disposal.
The encapsulation plant is a specialist industrial facility incorporating mechanical handling equipment, remote operation capabilities, radiation protection infrastructure, and associated electrical and control systems. Construction began in 2019, with the building subsequently handed over for installation of nuclear equipment in 2022. The development has since progressed through individual equipment tests and integrated commissioning exercises.
One of the principal engineering challenges is establishing reliable interfaces between equipment supplied for different stages of the disposal programme. Machinery must perform consistently within the physical and operational constraints of the facility, with monitoring and control systems providing information about equipment condition and availability. Maintenance and inspection requirements must also be accommodated within areas where direct access during normal operation will be restricted.
The integrated trial programme began in August 2024 using non-radioactive test elements. Posiva completed the first stage in September of that year, while the encapsulation plant’s trial operation continued into 2025. Those exercises examined the interaction between equipment, supporting infrastructure, and the personnel responsible for operating the facility.
Progress has also continued on the equipment required for underground disposal. In June 2026, Posiva reported further successful testing of specialist canister handling machinery. The equipment development programme includes verification of remote operation capabilities and the ability of individual machinery packages to function within the completed underground facility.
Commissioning the underground repository introduces additional engineering requirements beyond those associated with the encapsulation plant. Ventilation, electrical distribution, communications, monitoring, and maintenance infrastructure must remain available across an operating environment that will continue to develop throughout the lifetime of the facility. Equipment reliability and the availability of specialist technical support will consequently remain important long after the initial commissioning programme has concluded.
Unlike an electricity generating station, whose commercial output is measured in megawatt-hours, Posiva’s operational performance will be assessed partly through the volume of material it can safely manage over extended periods. The company anticipates disposing of approximately 30 to 40 canisters annually at the start of operations, potentially increasing throughput to around 60 canisters per year as the programme develops.
Maintaining that throughput will require coordination between equipment availability, inspection and maintenance activities, workforce planning, and the development of additional repository infrastructure. The initial operating programme is therefore intended to establish experience with the complete industrial process rather than immediately achieving its maximum anticipated annual capacity.
Finland’s government granted Posiva its operating licence on 22 October, following the publication of the Radiation and Nuclear Safety Authority’s safety assessment in August. The licence remains valid until the end of 2070 and covers both the encapsulation plant and the final disposal facility.
The regulatory decision follows more than four decades of preparation, research, engineering development, and safety assessment. Finland granted a construction licence in 2015, with construction of the disposal facility commencing towards the end of 2016. Posiva submitted its subsequent operating licence application in 2021.
Final disposal infrastructure addresses a responsibility extending beyond the generating lives of individual nuclear power stations. Establishing an operational disposal capability provides a long-term route for managing spent fuel that has accumulated during electricity generation, complementing the interim storage facilities already used by Finland’s nuclear operators.
The latest transport exercise marks another step towards that operational capability. Further commissioning activities and regulatory verification remain necessary before the facility begins handling actual spent fuel, with the completion of those requirements determining when Posiva can commence commercial-scale disposal operations.