TotalEnergies completes Steeple solar and storage acquisition

TotalEnergies completes Steeple solar and storage acquisition

TotalEnergies has acquired a consented solar development incorporating battery storage. The Nottinghamshire project combines approximately 450 MW of planned solar export capacity with a 150 MW battery installation, utilising existing transmission infrastructure near West Burton.


IN Brief:

  • TotalEnergies has completed its acquisition of the Steeple Renewables Project from RES.
  • The development has secured grid connection capacity of up to 600 MW following the decommissioning of West Burton A power station.
  • The solar and battery storage installation is expected to enter operation by the end of 2030.

TotalEnergies has completed its acquisition of the Steeple Renewables Project from RES, securing a large solar and battery storage development that will utilise electricity transmission capacity released by the closure of West Burton A power station in Nottinghamshire.

The consented development near Sturton-le-Steeple comprises approximately 450 MW of planned solar photovoltaic export capacity and a 150 MW battery energy storage installation. TotalEnergies expects the project to become operational by the end of 2030.

RES began developing Steeple in 2023, securing development consent from the Secretary of State for Energy Security and Net Zero on 9 October 2026. The corresponding development consent order came into force on 31 October, establishing the statutory framework for construction, operation, and maintenance.

The completed transaction transfers the development to TotalEnergies ahead of its main construction programme. The companies have not disclosed the acquisition’s financial terms.

A connection agreement with National Grid provides for up to 600 MW of combined capacity, making use of infrastructure associated with the adjacent West Burton generating complex.

The availability of that connection provides a significant advantage in progressing a development of Steeple’s scale. Securing sufficient network capacity has become an increasingly complicated aspect of renewable energy development, particularly where additional generation requires extensive transmission reinforcement before electricity exports can commence.

West Burton A previously accommodated approximately 2 GW of coal-fired generating capacity. Its closure in 2023 created an opportunity to accommodate different generating technologies within a region already connected to Britain’s high-voltage transmission infrastructure.

The electrical characteristics of those technologies differ from the synchronous generating equipment formerly operating at the coal-fired station. Photovoltaic generation and conventional battery storage generally connect to electricity networks through power electronic converters, rather than generators mechanically coupled to steam turbines.

Connecting inverter-based resources requires consideration of their response to network voltage and frequency disturbances, their reactive power capabilities, and the characteristics of fault currents delivered by their conversion equipment.

An existing transmission connection consequently provides a valuable development asset, but does not remove the requirement for electrical studies, equipment design, and compliance testing appropriate to the technologies replacing the former generating capacity.

Steeple’s photovoltaic installation will require collection circuits connecting its generating arrays to central electrical infrastructure. Inverters will convert electricity produced by the modules into alternating current, with transformers increasing the voltage for subsequent transmission.

The project’s approximately 450 MW solar export figure should be distinguished from the combined nominal direct current rating of the installed photovoltaic modules. Developers may select module and inverter capacities that differ from the permitted network export rating, depending on expected generation profiles and equipment costs.

TotalEnergies estimates that Steeple’s annual electricity generation would be equivalent to the consumption of approximately 180,000 UK households. Applying the annual household consumption figure of 3,323 kWh used in the company’s assessment produces an implied generation forecast of approximately 598 GWh annually.

That estimate describes expected annual production rather than the availability of electricity at individual times of day. The accompanying 150 MW battery introduces a controllable element to the project’s output, enabling electricity to be stored for subsequent dispatch.

The battery’s power rating establishes the rate at which it can deliver electricity, while its energy capacity will determine the period over which that output can be sustained. TotalEnergies has not disclosed a confirmed megawatt-hour specification for the installation.

Coordinating solar generation and battery operation creates opportunities to utilise the electricity connection across different periods. Photovoltaic production will predominantly determine generation during daylight hours, while stored electricity may be exported after solar output declines.

The extent to which the battery can also participate in electricity trading and flexibility services will depend on the commercial arrangements established for the project, its permitted operating modes, and the technical qualification requirements of individual markets.

Supervisory control systems must regulate the operation of both generating and storage equipment within the connection’s import and export limits. Their coordination will be particularly important if simultaneous photovoltaic generation and battery discharge approach the maximum electrical capacity available to the development.

The transaction advances TotalEnergies’ strategy of combining renewable generation, flexible assets, storage, and electricity trading. The company reported nearly 38 GW of gross renewable generating capacity at the end of October, with a target of exceeding 100 TWh of net electricity production by 2030.

At Steeple, development consent and the ownership transfer establish the basis for progressing detailed engineering, equipment procurement, and construction. Finalising the storage specification and associated electrical infrastructure will determine the project’s operating capabilities ahead of its planned entry into service by the end of 2030.


  • TotalEnergies completes Steeple solar and storage acquisition

    TotalEnergies completes Steeple solar and storage acquisition

    TotalEnergies has acquired a consented solar development incorporating battery storage. The Nottinghamshire project combines approximately 450 MW of planned solar export capacity with a 150 MW battery installation, utilising existing transmission infrastructure near West Burton.