IN Brief:
- Terna has published the geographic microzones used for connection planning on Italy’s transmission grid.
- A September 2026 decree provides for subsequent calculations of additional renewable and storage capacity.
- The published boundaries do not constitute connection offers or available capacity allocations.
Terna has made Italy’s transmission grid microzones available to connection applicants, creating a published territorial reference for the next stage of renewable generation and storage planning. The national transmission operator released the subdivision on 19 November under a methodology approved by the Ministry of the Environment and Energy Security. The move implements part of Ministerial Decree No. 291, dated 8 September 2026, which sets out a framework for assessing additional renewable and storage capacity that electricity networks could accommodate.
The new information identifies the areas in which assessments will be carried out; it does not state how much additional capacity is currently available in each one. Terna must still calculate the maximum extra generation and storage that could be integrated under the approved methodology. A microzone boundary is therefore neither an offer of grid access nor a guarantee that an individual project can connect without further network work.
Italy’s electricity system is organised into market zones, but the main limitations affecting a proposed connection can be much more localised. Thermal ratings on circuits, transformer capacity, network voltage, fault levels and power flows between substations can all limit the amount of additional injection a particular part of the system will accept. A subregional modelling area gives the transmission operator a more detailed basis for examining those conditions than a single national or regional capacity number. The microzone boundaries are therefore a planning input, not a substitute for engineering assessments of individual sites.
Terna has previously described an approach involving 76 microzones within its wider efficient territorial planning programme. The divisions allow the operator to model transmission constraints inside defined areas and evaluate connections against network developments. Its planning process also draws on the T.E.R.R.A. platform, introduced to bring together transmission reinforcement plans, renewable generation proposals, storage projects and other connection requests. Data are made available to relevant ministries, regulators, regional authorities and other stakeholders, supporting more coordinated infrastructure decisions.
The need for more granular planning has grown alongside Italy’s large queue of renewable and storage applications. Proposed generating capacity can substantially exceed the volume that ultimately reaches construction, while multiple applicants may be seeking capacity in the same constrained part of the network. Engineers have to assess which proposals could operate together, where reinforcement would be required and whether planned transmission developments would alter the result. The published microzones provide a consistent geographic unit for that modelling, without prejudging which schemes will go ahead.
Ministerial Decree 291 establishes criteria for determining and updating the maximum additional capacity from renewable sources and storage that may be integrated into different portions of the national grid. Those calculations must sit alongside energy policy objectives and the technical capacity available. The rules also form part of Italy’s response to virtual grid saturation, in which requests can occupy planning capacity without necessarily representing projects likely to be delivered. Translating the decree into operating procedures will require more than drawing boundaries: available capacity has to be calculated, reviewed and linked to connection processes.
The new map does not remove the physical work required to integrate a generator. Transmission connection still depends on suitable equipment and network protection, the design of connection bays and transformers, and the ability of the system to operate securely under changing generation and demand conditions. Storage projects add another operating dimension because they can both export electricity and import it for charging. A connection study may therefore consider constraints under different dispatch and charging scenarios, not merely the nameplate output of the equipment.
Individual connection requirements will continue to depend on a project’s location, export rating, operating profile and the electrical conditions at its proposed interface. Two installations within the same microzone may encounter different substation constraints or require different protection and transformer arrangements. Applicants must still submit project-specific technical information through Terna’s connection process, and any capacity figure subsequently published for a zone will need to be interpreted against those physical constraints.
Terna’s next step is to apply the approved method to calculate additional capacity across the published areas. Those assessments will provide a more informative basis for administering future connection requests, but their usefulness depends on how regularly they are updated and how clearly the network constraints are explained. For now, the 19 November publication establishes the map on which that subsequent technical work will be based.