IN Brief:
- Ofgem says most projects in the reformed queue have later connection dates than before reform.
- The regulator will investigate protected and Phase 1 offers and require better explanations from NESO and networks.
- Incentive changes, compensation arrangements and possible enforcement remain under consideration, not final decisions.
Ofgem has opened an urgent inquiry into grid connection delays affecting protected and Phase 1 projects in Great Britain. The regulator says most projects remaining in the reformed queue have received later connection dates than those in their earlier offers, despite substantial removal of speculative capacity. It is asking the National Energy System Operator (NESO) and network companies to investigate the causes and identify whether deliverable dates can be brought forward.
The reform was intended to replace an overcrowded queue with a sequence of projects more likely to progress. Ofgem says removing speculative capacity should reduce the network infrastructure that would otherwise need to be planned, but queue reductions have not translated into earlier dates for most retained applicants. The inquiry will examine whether the changes arise from construction planning assumptions, network delivery requirements or decisions that differ between connection areas and companies.
Protected and Phase 1 projects have already been through the revised offers process, making the changed dates a live issue for construction schedules and investment decisions. A developer may have to resequence land agreements, transformer procurement, substation construction or commissioning when the grid connection moves back. Some delays may result from physical reinforcement works shared with other projects; others may reflect planning assumptions or delivery performance. Ofgem has not attributed all the delayed offers to a single cause.
Construction Planning Assumptions influence which transmission works and reinforcements are included when NESO and network companies prepare connection offers. Ofgem is asking the National Energy System Operator to release more information about those assumptions and develop clearer rules with industry input. Different treatment of shared network works or future reinforcement schemes can change the date offered to a project, even where its own site works are progressing. The inquiry will examine how those planning assumptions have been applied across connection offers and which resulting delays could be avoided.
Ofgem is also seeking clearer information about revised offer dates and why they differ from earlier forecasts. The regulator wants networks and NESO to report dates as offers are issued, so the effect of individual reinforcement schemes and planning assumptions can be scrutinised. A connection held up by a named substation upgrade has a different delivery path from one affected by a broad assumption about future network works. The inquiry is intended to expose those distinctions rather than treat every delayed applicant as an identical case.
Ofgem is also considering financial commitments for oversubscribed technologies, particularly batteries, and measures to address speculative or non-viable data centre requests. NESO is expected to monitor accepted offers against delivery milestones and intervene when projects fail to demonstrate adequate progress. These changes are intended to prevent reserved connection capacity from remaining tied to stalled proposals, without treating every delayed project as unviable. Their effectiveness will depend on consistent monitoring and transparent assessment of the milestones in each connection agreement.
Ofgem is exploring automatic compensation where network companies cause connection delays and says connection agreements need not wait for a new universal compensation scheme to include such provisions. Separately, it plans reforms to permit customers to build and transfer certain transmission connection assets and to enable independent transmission ownership under an appropriate licence. Both proposals concern future arrangements; neither makes all existing delays eligible for compensation or immediately changes the licence status of completed assets.
Network companies will face further scrutiny through the RIIO-3 connections incentive, which Ofgem says can reward or penalise performance. A consultation on the baseline for that incentive is expected in December 2026. The regulator also plans more frequent disclosure of network delivery and connection performance, beginning with its Infrastructure Progress Report in February 2027. Any performance framework will need to distinguish delays within a company’s control from those arising through wider network dependencies; the consultation will establish how the incentive baseline is set.
The regulator has reserved enforcement action for cases in which the inquiry finds evidence of a material breach of licence obligations by NESO or a network company. No such finding has been made through the inquiry announcement. Ofgem expects to consult on the RIIO-3 incentive baseline in December and publish connection outcome data in its February 2027 Infrastructure Progress Report. Those disclosures will provide the first formal checkpoints for testing whether the changes to the queue are delivering more dependable connection dates.