IN Brief:
- AIS will supply 55 NjordGuard cable protection systems and 54 associated bellmouths.
- The generating installation will incorporate 66 kV inter-array circuits and two 154 kV export cables.
- The protection systems have a specified design life of 28 years, with deliveries scheduled for completion in August 2027.
AIS has secured a contract from South Korean marine infrastructure contractor LS Marine Solution to manufacture cable protection equipment for the Shinan-Ui offshore wind farm, supporting the electrical infrastructure connecting its turbines to the mainland electricity network.
The British engineering company will supply 55 NjordGuard cable protection systems and 54 associated bellmouths for the 390 MW development, located approximately four kilometres south of Uido Island.
Project engineering will begin immediately, with deliveries to South Korea scheduled for completion in August 2027. The protection systems have been designed to meet a specified service life of 28 years.
A 66 kV inter-array network will collect electricity generated by the wind turbines and convey it to an offshore substation. Two 154 kV export cables will subsequently transmit electricity towards shore, with AIS supplying protection equipment for both parts of the electrical network.
The contract concerns the mechanical protection of power cables at their interfaces with offshore infrastructure. Although submarine cables incorporate armour and protective outer layers, the sections approaching turbine foundations and substations can experience substantially different mechanical loading from buried sections of the same cable route.
Where a cable emerges from the seabed before entering a foundation, the unsupported section can be exposed to hydrodynamic forces that cause movement and repeated bending. Contact with rock scour protection or structural surfaces introduces further potential for abrasion.
The protection system must limit those effects without restricting the cable’s movement beyond its permissible mechanical characteristics. Excessive bending can damage internal components, while repeated flexing can contribute to fatigue over the installation’s operating life.
NjordGuard has been developed for offshore wind installations incorporating monopile and J-tube interfaces. Its design accommodates the transition between the seabed and supporting structures, where cable geometry and exposure to marine conditions must be considered together.
The system incorporates AIS’s Uraduct polyurethane material, certified under API 17L, to provide resistance to abrasion. Protecting the cable against contact with surrounding surfaces can reduce the requirement for additional rock placement intended to stabilise exposed sections, depending on the installation’s specific engineering requirements.
AIS has also designed the protection equipment for assembly aboard installation vessels. Reducing the amount of assembly work undertaken offshore can simplify cable installation activities, where available vessel space, lifting arrangements, and suitable marine conditions constrain working time.
The associated bellmouths form part of the interfaces through which cables enter offshore structures. Their geometry guides the cable into its required position while reducing the risk of concentrated mechanical loading where it passes through an aperture or tubular guide.
Engineering those interfaces requires information from both the structural and electrical equipment suppliers. Cable diameter, minimum bending radius, installation tension, and foundation geometry influence the dimensions and mechanical characteristics required of the protection equipment.
Those requirements must also be reconciled with the cable’s thermal performance. Electrical current produces heat through conductor resistance, while the surrounding materials determine how effectively that heat can dissipate into the marine environment.
Additional protection can alter the thermal conditions around a cable, particularly where it passes through enclosed structural interfaces or other sections with restricted heat transfer. Cable rating assessments must therefore account for the protection configuration as well as burial depth, seabed properties, and expected electrical loading.
The different voltage ratings of Shinan-Ui’s inter-array and export cables reflect their respective functions. Inter-array circuits aggregate electricity from individual generating units, while the export circuits carry larger combined power flows away from the offshore substation.
Increasing the transmission voltage reduces the current needed to convey an equivalent amount of power, helping manage resistive losses and conductor requirements. The choice of voltage also influences insulation, termination, and equipment specifications throughout the electrical system.
Damage to an inter-array cable can interrupt generation from several turbines, depending on the network configuration and available alternative electrical paths. A fault affecting an export circuit can restrict electricity transmission from a considerably larger portion of the development.
Offshore repair operations may require specialist vessels, replacement cable sections, jointing equipment, and suitable weather conditions. Designing cable protection around the expected mechanical and environmental conditions can reduce exposure to failures whose repair requirements extend well beyond replacement of the damaged electrical component.
AIS has previously supplied protection equipment for international offshore wind developments, including projects in Taiwan involving Asian cable suppliers and European developers. The Shinan-Ui contract extends that work into South Korea’s offshore electricity infrastructure programme.
The immediate engineering programme will establish the protection equipment’s final configuration against the cable and structural interfaces selected for Shinan-Ui. Manufacturing and delivery must then be coordinated with the wider procurement programme ahead of the August 2027 deadline.



