News

—



  • SSEN extends Aberdeen 132kV cable replacement works

    SSEN is extending works on Aberdeen’s underground transmission cable replacement. Water ingress in existing ducts has blocked the final cable section on the 5km double-circuit 132kV Redmoss–Clayhills route.


  • Cloudberry completes Nordic renewable platform acquisition

    Cloudberry has completed its acquisition of Orrön’s Nordic renewable platform. The transaction adds 758GWh of annual proportionate generation and raises Cloudberry’s portfolio to approximately 2.1TWh across Nordic electricity markets.


  • Nordseecluster A turbine installation reaches halfway point

    Nordseecluster A has reached halfway through its turbine installation programme. RWE has installed 22 of 44 15MW turbines, with staged commissioning under way before full 660MW grid connection in early 2027.


  • SSEN extends Aberdeen 132kV cable replacement works

    Dumbrava battery storage has secured €19 million for construction financing. The 50MW/100MWh Romanian project is already under construction, with commercial operation targeted for April 2027.


  • ENTSO-E sets grid infrastructure security priorities

    ENTSO-E has set seven priorities for securing Europe’s transmission infrastructure. The proposals cover physical protection, cybersecurity, offshore recovery, crisis responsibilities, cross-border resources, information controls, and dedicated security investment.


  • SSEN extends Aberdeen 132kV cable replacement works

    SPIE will deliver electrical infrastructure for two Belgian battery projects. Volta and Franklin combine 300MWh of storage with 150kV transmission connections and commercial commissioning planned during 2027.


  • SSEN extends Aberdeen 132kV cable replacement works

    SUNOTEC has started construction of its Stendal battery storage project. The 100MW/441MWh system includes a new 110kV substation and is scheduled for commissioning in the first quarter of 2027.


  • SSEN extends Aberdeen 132kV cable replacement works

    Sirius battery has reached financial close in the northern Netherlands. Vattenfall will control dispatch of the 200MW/800MWh system under a long-term tolling agreement tied to time-dependent transmission rights.


  • Cloudberry completes Nordic renewable platform acquisition

    Borkum Riffgrund 3 has entered commercial operation in German waters. The 913MW offshore wind farm combines 83 turbines with 786MW of long-term corporate power purchase agreements.


  • UK public EV charging reaches 121,171 chargers

    Britain’s public EV charging network reached 121,171 chargers in July. Almost 29,000 were rated at 50kW or above, while regional figures continue to show sharply different infrastructure mixes.