PLUG Charging has established an internal electrical infrastructure maintenance division. The Cardiff-based operator is expanding its engineering capabilities following a series of acquisitions, bringing inspection, testing, servicing, and fault response under its own management.
Power On has secured Siemens Energy’s Corby electricity connection contract. The 2.6 MVA connection will use an existing GTC primary substation, bringing forward the anticipated availability of power from 2029 to May 2027.
NeuConnect has begun installing nearshore electricity cables in northern Germany. Prysmian is delivering a 30 km installation programme at Wilhelmshaven, advancing construction of the £2.4 billion interconnector between Britain and Germany.
SP Energy Networks has completed its Hunterston transmission substation extension. The £13 million investment incorporates four additional 400 kV switchgear bays, a 200 MVAr shunt reactor, and Hitachi Energy’s alternative insulation technology.
Green Volt has reserved turbine capacity for Scottish floating wind. The Siemens Gamesa agreement covers 28 turbines exceeding 15 MW each, alongside a separate Aberdeen port arrangement supporting £15 million of infrastructure and supply chain expenditure.
CWIEME Berlin is expanding its electrical manufacturing programme for 2027. New exhibition areas will address factory automation, grid logistics, transformer lifecycle management, and switchgear manufacturing, alongside the inaugural Grid Delivery Summit.
Montenegro’s Bogetići solar project has advanced towards securing project financing. Nu Energy and Investment has signed an EBRD mandate letter for the €63 million development, incorporating a 65 MW/130 MWh battery storage installation.
Hanersun and Electrical One have agreed a Hungarian storage partnership. Their initial 45 MWh project includes nine liquid-cooled battery containers and integrated electrical substations, alongside plans to establish European servicing capabilities.
Nordseecluster B has received its first offshore wind turbine foundations. Ten monopiles have arrived at Eemshaven ahead of offshore construction for RWE’s 900 MW German North Sea development.
Posiva has completed a further Finnish nuclear fuel transport test. The exercise used the operational spent fuel transfer cask at Olkiluoto as commissioning continues ahead of the commencement of final disposal activities.