National Grid highlights demand connection reform requirements

National Grid highlights demand connection reform requirements

National Grid has highlighted growing pressure on electricity demand connections. Data centres account for an estimated 62–70 GW within the demand connection queue, intensifying scrutiny of how Britain allocates prospective network capacity.


IN Brief:

  • National Grid's strategic demand director has highlighted the disparity between prospective electricity connection requirements and existing consumption.
  • Ofgem previously identified an increase in contracted demand connection offers from 41 GW to 125 GW between November 2024 and June 2025.
  • Proposed reforms encompass financial commitments, project progression milestones, strategic prioritisation, and alternative connection delivery arrangements.

National Grid has highlighted the scale of prospective electricity demand competing for access to Britain’s network, with data centres accounting for an estimated 62–70 GW within the demand connection queue. David Adkins, the company’s strategic demand director, outlined the challenge on 23 November as regulators and network operators continue developing reforms to the allocation and delivery of electricity connections.

Speaking on Monday, Adkins compared the prospective requirements of data centre developers with national peak electricity demand of approximately 45 GW. He also referred to the government’s ambition for 6 GW of data centre capacity by 2030, illustrating the disparity between the capacity being requested through the connections process and anticipated development requirements.

National Grid Electricity Transmission previously identified approximately 70 GW of directly connected demand within its updated connection queue in August. The figure describes prospective projects seeking access to its transmission infrastructure, rather than electricity currently being consumed or demand expected to materialise simultaneously.

The estimates illustrate a difficulty facing network operators when determining the infrastructure required to accommodate future electricity consumption. Connection applications establish potential requirements, but the commercial and technical readiness of individual developments can vary considerably. Some projects may change their equipment specifications, construction schedules, or proposed locations before progressing into operation.

Ofgem identified a substantial increase in contracted demand connection offers earlier this year, reporting growth from 41 GW in November 2024 to 125 GW in June 2025. Applications associated with data centres accounted for much of that expansion, prompting proposals to introduce additional financial commitments and project progression requirements for prospective developers.

The regulator’s demand connections reform programme encompasses three areas of work, designated Curate, Plan, and Connect. Together, they address the commercial and technical readiness of applicants, strategic allocation of available capacity, and alternative arrangements through which connection infrastructure could be delivered.

Under proposals published in July, qualifying data centre developers would need to provide financial commitments between accepting a connection offer and becoming ready to connect. Additional milestones would require evidence of project development, including financial and technical capability, commercial maturity, and procurement activity, to retain access to reserved network capacity.

Establishing those requirements involves balancing the need to remove speculative projects against the circumstances of commercially credible developments. Industrial customers may depend on confirmation of electricity availability before committing to building construction or equipment purchases. Requiring substantial investment too early in the process could create difficulties for projects whose feasibility is directly linked to their prospective connection date.

Strategic allocation of capacity also has implications for the geographical distribution of future electrical infrastructure. Additional demand concentrated within particular regions can create requirements for new substations, transformers, and transmission circuits, even where spare capacity exists elsewhere. Assessing applications alongside wider electricity system requirements can help identify where reinforcement investment will support several developments rather than a single prospective customer.

Ofgem has separately consulted on expanding the scope of self-build and transfer arrangements for transmission connection assets. Its proposals would allow eligible customers to construct certain infrastructure dedicated to their own connection before transferring ownership to the relevant transmission operator. These arrangements could provide developers with greater control over aspects of equipment procurement and construction, subject to technical compliance and the capacity available on the wider network.

Flexible connection arrangements provide another potential means of improving access to electrical infrastructure. Customers able to modify their consumption during periods of network constraint may be able to operate under different connection conditions from those requiring unrestricted access to their full contracted capacity. The suitability of such arrangements depends on the customer’s operating requirements and the electrical characteristics of the network.

Experience with the existing generation and storage connection reforms demonstrates the difficulty of translating changes in queue management into earlier physical connections. On 19 November, Ofgem launched an inquiry into delayed connection offers affecting protected and first-phase projects whose revised dates were later than those previously offered.

Although reducing the number of speculative applications can provide a clearer view of future electricity requirements, physical infrastructure remains a central consideration. Network capacity can only be made available within the operating limits of existing equipment or through completed reinforcement works, creating dependencies on engineering resources, equipment procurement, construction, and commissioning.

National Grid’s latest assessment highlights the need to establish more reliable information about prospective electricity consumption alongside arrangements for delivering the required infrastructure. The remaining demand connection reforms will influence how network capacity is allocated between competing commercial and industrial developments and how the associated engineering investment is prioritised.


  • National Grid highlights demand connection reform requirements

    National Grid highlights demand connection reform requirements

    National Grid has highlighted growing pressure on electricity demand connections. Data centres account for an estimated 62–70 GW within the demand connection queue, intensifying scrutiny of how Britain allocates prospective network capacity.