Sri Lanka connects first grid-scale battery

Sri Lanka connects first grid-scale battery

Sri Lanka has connected its first grid-scale standalone battery system. The 10MW/40MWh Anuradhapura installation begins a wider 130MW/520MWh storage programme spanning 13 sites.


IN Brief:

  • The Anuradhapura BESS provides 10MW of power and 40MWh of storage, giving four hours of nominal duration.
  • The wider portfolio totals 130MW/520MWh across 13 sites, with further installations progressing towards commissioning.
  • The systems are intended to provide solar shifting, frequency response, peak support, and voltage regulation.

WindForce PLC and Vidullanka PLC have commissioned a 10MW/40MWh battery energy storage system at Anuradhapura, bringing the first installation in a wider 130MW/520MWh Sri Lankan storage programme onto the national grid.

The Anuradhapura plant has four hours of nominal storage at its rated 10MW output and is being delivered through StoreX, a joint venture in which WindForce holds 51% and Vidullanka 49%. The project was connected to the grid on 18 September.

The broader portfolio consists of 13 installations with a combined 130MW of power and 520MWh of storage. Twelve sites are being developed through StoreX, while a separate 10MW/40MWh project at Vavunathivu continues under the partners’ Solar Universe joint venture.

Anuradhapura provides the first operating asset within that programme. The battery is designed to charge during periods of surplus electricity, particularly when daytime solar generation is strong, and discharge later as demand rises after sunset.

That operating pattern addresses a growing intraday mismatch on electricity systems with expanding photovoltaic capacity. Solar production can be abundant during daylight hours but falls rapidly towards the evening, when domestic and commercial demand can remain high.

A four-hour battery gives the system operator a larger energy reservoir for moving electricity between those periods than a short-duration frequency-response installation. At full nominal output, 40MWh allows the Anuradhapura plant to sustain 10MW for four hours before conversion losses, operating reserves and state-of-charge constraints are taken into account.

The portfolio is also intended to provide fast-frequency response, peak-load shifting and voltage regulation. Those services depend on the power-conversion systems and controls around the battery rather than the cells alone.

Frequency response requires rapid changes in active-power output when system frequency moves away from its target. Battery inverters can respond quickly provided sufficient charging or discharging headroom is available, giving storage a role in balancing sudden differences between electricity supply and demand.

Voltage support instead relies substantially on reactive-power control and local network conditions. Modern inverter systems can provide or absorb reactive power within equipment limits, allowing a battery to contribute to voltage management without necessarily moving large quantities of stored energy at the same time.

The grid connection therefore involves more than exporting stored electricity. Protection, metering, communications, harmonic performance, fault behaviour and control interfaces have to be coordinated with the surrounding network before the installation can be relied upon for operational services.

Anuradhapura also provides commissioning experience that can be applied to the remaining projects. Repeating 10MW/40MWh blocks creates opportunities to standardise battery containers, power-conversion equipment, control systems and operating procedures across multiple sites, although each location still requires its own civil works, transformers, switchgear and connection engineering.

Distributed deployment changes the system impact compared with constructing a single 130MW battery. Multiple sites can place flexibility closer to different network constraints and renewable-generation areas, while also reducing dependence on one connection point. The trade-off is a larger number of individual assets to communicate with, maintain and coordinate.

Corporate disclosures show that the StoreX structure was revised during 2026, with WindForce taking 51% and Vidullanka 49%. The 12 StoreX projects account for 120MW/480MWh of the total portfolio, while Vavunathivu adds the remaining 10MW/40MWh under the separate Solar Universe structure.

That distinction is important because contemporary reporting has sometimes described all 13 locations as StoreX projects. The aggregate national programme remains 130MW/520MWh, but the corporate structure divides delivery between the 12-site StoreX portfolio and the separate Vavunathivu joint venture.

The projects are being developed as long-term grid infrastructure rather than batteries dependent solely on short-term wholesale trading. Structured capacity revenues give the developers a defined commercial basis while providing the power system with contracted flexible capacity as renewable generation expands.

Storage does not remove the need for transmission reinforcement, conventional generation or sufficient energy supply during prolonged low-renewable periods. A battery moves electricity through time rather than creating it, and its support is ultimately constrained by available megawatt-hours.

The immediate Sri Lankan requirement is more specific: absorb electricity that would otherwise be difficult to use during solar-rich daylight periods and return part of it when the evening system needs additional supply. With Anuradhapura now connected, the remaining projects can move through commissioning against an operating reference rather than a purely planned design.

Performance across the completed fleet will ultimately be measured through availability, charging during renewable-surplus periods, discharge during peak demand and delivery of frequency and voltage services. Those operating results will determine how effectively the 13-site programme converts 520MWh of installed battery capacity into usable flexibility for Sri Lanka’s electricity network.


  • Innergex joins 1 GW Québec wind partnership

    Innergex joins 1 GW Québec wind partnership

    Three partners have formalised plans for large-scale Québec wind development. Innergex will coordinate development and construction in the Wocawson area, which has estimated generating potential of approximately 1 GW.


  • Peak Energy expands sodium-ion financing to $157m

    Peak Energy expands sodium-ion financing to $157m

    Peak Energy has expanded financing for sodium-ion battery manufacturing operations. Its $157 million package includes a $25 million HSBC debt facility to support project deliveries from 2027.