GE Vernova leads 6GW Indian HVDC terminal bid

GE Vernova leads 6GW Indian HVDC terminal bid

GE Vernova leads India’s bidding for a 6GW HVDC package. The company is L1 for ±800kV converter terminals linking Barmer II and South Kalamb, with final award formalities still outstanding.


IN Brief:

  • GE Vernova T&D India has emerged as L1 bidder for two 3GW, ±800kV LCC HVDC terminal blocks.
  • The converter stations form part of a transmission corridor intended to evacuate 6GW of solar generation from Rajasthan's Barmer complex.
  • L1 status is not a final order, and POWERGRID must complete its remaining procurement formalities before any contract is secured.

GE Vernova T&D India has emerged as the lowest bidder for a 6,000MW, ±800kV high-voltage direct-current converter-terminal package being procured for the Barmer II to South Kalamb transmission corridor.

The company said Power Grid Corporation of India had informed it on 7 September that it held L1 status for the design and establishment of the line-commutated converter terminal stations. The proposed package comprises two 3,000MW converter blocks and associated engineering and equipment.

L1 status is a procurement milestone rather than a final contract award. It identifies GE Vernova T&D India as the technically qualified bidder with the lowest commercial offer, but POWERGRID must complete its remaining formalities before issuing a final order. The company has not disclosed a contract value and says execution would take place over several years if the award proceeds.

The converter terminals form part of a much larger transmission scheme intended to evacuate renewable electricity from Rajasthan. POWERGRID’s tender documentation identifies the project with Rajasthan Renewable Energy Zone Phase IV, Part 5, covering 6GW of solar generation in the Barmer complex and transmission towards South Kalamb.

Separate line packages are being procured for the ±800kV HVDC bipole, meaning the terminal work represents one part of an extensive point-to-point transmission system. Converter stations at each end have to transform alternating current into direct current for long-distance transmission and then convert it back before injection into the receiving AC network.

HVDC is particularly suited to bulk transfers over long distances because it provides controllable power flow and avoids some of the reactive-power and charging-current constraints associated with long AC lines. At 6GW, however, the terminal stations themselves become major system assets whose controls and protection have to manage very large changes in power flow without destabilising the surrounding networks.

The Barmer project uses line-commutated converter technology. LCC systems rely on thyristor valves and remain established technology for high-capacity, point-to-point HVDC links connected between sufficiently strong AC systems. Their scale brings substantial requirements for converter transformers, valve halls, harmonic filtering, reactive-power compensation, cooling, controls, protection, and high-voltage switchgear.

A disturbance that removes several gigawatts of transfer suddenly can affect frequency and reserve requirements across a wide area. The control system therefore has to regulate normal power transfer while coordinating protection for faults on the DC line, converter equipment, or either connected AC network. Recovery from disturbances is as important as steady-state efficiency when a corridor carries output comparable with several large generating stations.

The transmission programme is being developed because generation and demand are geographically separated. Rajasthan has some of India’s strongest solar resources, while large centres of electricity demand lie hundreds of kilometres away. Renewable capacity can be constructed faster than major interstate transmission, creating a risk that generation reaches completion before enough network capacity exists to move its output.

POWERGRID’s tender specifically associates Barmer II with 6GW of solar evacuation. That makes the converter-terminal procurement part of the renewable project delivery chain rather than a general network upgrade: solar modules and inverters can produce electricity only when transmission lines, substations, converter stations, protection, and system-control infrastructure are available to carry it.

India already has operating experience with high-capacity HVDC, and POWERGRID has identified Barmer to South Kalamb as an LCC-based corridor within its wider development pipeline. The choice of established converter architecture reduces technology novelty, but it does not reduce the industrial scale of manufacturing and installation required for a two-terminal, 6GW scheme.

Converter transformers are among the most specialised items because they have to handle the electrical stresses created by both the AC grid and converter valves. Thyristor assemblies, cooling systems, filters, control platforms, and protection equipment also have long manufacturing, testing, and qualification cycles, while site installation has to coordinate civil construction with high-voltage equipment and commissioning.

If the award is completed, GE Vernova T&D India’s scope would therefore extend well beyond supplying individual products. The project would require integrated design, manufacturing, delivery, construction support, testing, and commissioning across terminal equipment that has to operate as one transmission system despite being installed at opposite ends of the corridor.

Other Barmer–South Kalamb line packages have already been progressing through POWERGRID’s tender programme, reinforcing the need for terminal and overhead-line schedules to remain coordinated. An HVDC converter station completed without its line cannot transfer the intended power, while an energised line without operational converter terminals is equally unusable.

For now, that delivery sequence has not yet started under a final GE Vernova award. The technically significant development is that the company has reached the leading commercial position for a 6GW LCC package tied directly to renewable evacuation. The next milestone is contractual: only after POWERGRID completes the procurement can equipment orders, manufacturing schedules, site execution, and commissioning become firm commitments.


  • Global nuclear generation reaches record 2,702TWh

    Global nuclear generation reaches record 2,702TWh

    Global nuclear reactors generated a record 2,702TWh of electricity worldwide. World Nuclear Association says 82GWe is now under construction, while its conditional 2050 capacity scenario reaches 1,457GWe.


  • GE Vernova leads 6GW Indian HVDC terminal bid

    GE Vernova leads 6GW Indian HVDC terminal bid

    GE Vernova leads India’s bidding for a 6GW HVDC package. The company is L1 for ±800kV converter terminals linking Barmer II and South Kalamb, with final award formalities still outstanding.