IN Brief:
- East West Rail has issued a contract award notice naming UK Power Networks Operations for relocation of the 132 kV Cut Throat Lane switching station.
- The stated contract value is approximately £22.08m excluding VAT, covering design, decommissioning, installation, testing and commissioning.
- The later award notice specifies 27 November as the planned contract signature date after a standstill ending 26 November; neither contract execution nor a construction start is confirmed.
East West Rail Company has issued a contract award notice naming UK Power Networks Operations for the proposed relocation of the Cut Throat Lane 132 kV switching station north of Bedford. The work is valued at approximately £22.08 million excluding VAT and is needed because the existing installation occupies land required for a proposed six-track railway corridor.
The 16 November 2026 notice identifies UK Power Networks Operations as the intended supplier and records an ex-VAT price of £22,076,599. It follows a transparency notice published on 11 November. The later award record specifies a standstill period ending on 26 November and a planned contract signature on 27 November, so the project remains at a procurement milestone pending formal execution.
At Fairfield Park, also identified as Cut Throat Lane, East West Rail’s route proposals intersect existing electricity distribution infrastructure. The switching station must be relocated in a coordinated sequence so that the railway corridor can be developed while the utility maintains an operable high-voltage network. The electricity work is a specific enabling package within the larger transport programme and carries its own design, safety and commissioning requirements.
The proposed contract covers design, removal from service and relocation of the existing equipment, installation of a replacement 132 kV switching station, associated electrical and civil works, testing and commissioning. Public procurement documents set out the functional scope but provide no equipment schedule, final compound footprint or detailed circuit design. The value therefore describes a defined package of network alterations without identifying the individual switchgear assemblies or cable quantities to be procured.
A 132 kV switching station enables sections of a high-voltage network to be connected, isolated and protected. Circuit breakers interrupt fault current when protection systems detect defined abnormal conditions, while isolators provide visible separation for safe maintenance after a circuit has been de-energised. Relocation has to preserve the necessary connections and protection functions as well as the station’s physical access and safety clearances.
The engineering sequence will require designers to establish how existing circuits connect through the site, then provide equivalent paths through the replacement arrangement. Earthing performance, switchgear fault ratings, control and protection settings, cable terminations and communications interfaces must be suitable for the network. The published notice does not specify whether individual incoming circuits will be diverted overhead or underground, or which manufacturers will supply the replacement plant.
Continuity of supply is an explicit procurement requirement. Establishing the new installation before transferring circuits would allow elements of the old station to be removed in controlled stages, subject to the network operator’s approved switching plans. Testing and energisation must be sequenced around the available network configuration and protection arrangements. The exact transfer sequence, outage requirements and dates have yet to be published.
The award uses a direct procedure because the documented work is described as non-contestable activity on electricity network assets owned and operated by UK Power Networks Operations. Under the statutory responsibilities identified in the procurement notice, the relevant licensed distribution network operator retains the authority and technical responsibility to undertake the alterations. The procurement justification is tied to those network rights and obligations rather than a comparison of competing construction tenders.
The notice lists an intended contract period from 27 November 2026 to 19 November 2033. That period can cover design development, interface management, staged construction, commissioning and subsequent contractual responsibilities; it is not a programme showing seven years of continuous installation activity. East West Rail has not published a confirmed date for energising the replacement switching station or releasing the original site to railway contractors.
The railway and electrical works have to be coordinated within the same constrained corridor. Rail infrastructure requires clearances and safe construction access around its proposed alignment, while the utility must retain suitable access to live electrical equipment and preserve separation from public and railway activity. Final cable routes, station access, earthing design and safe working boundaries will need to be resolved alongside the railway design before a transfer of services is authorised.
East West Rail is developing connections between Oxford, Milton Keynes, Bedford and Cambridge, with construction and associated utility diversions taking place through multiple packages. The Cut Throat Lane work concerns one high-voltage installation north of Bedford rather than the entire railway construction programme. The existing station’s removal will depend on completion and acceptance of the replacement electrical arrangements within that programme.
The immediate next step is execution of the proposed direct-award contract after the stated standstill period. Engineering coordination, detailed design and agreement on the switching and commissioning sequence will determine subsequent delivery dates. As of the 16 November award notice, UK Power Networks Operations has been named for the work, but no start on site or commissioning timetable has been confirmed.