Linjemontage selected for SEK 1bn transmission project

Linjemontage selected for SEK 1bn transmission project

Linjemontage has been selected for a Swedish transmission construction project. Svenska kraftnät’s procurement covers approximately 98 km of new 400 kV overhead infrastructure between Ekhyddan and Nybro, with completion targeted for 2030.


IN Brief:

  • Svenska kraftnät has issued a procurement award decision worth approximately SEK 1 billion to Linjemontage.
  • The proposed 98 km transmission line will reinforce electricity transfer capacity and operating resilience across southeastern Sweden.
  • The agreement remains subject to a statutory standstill period, with construction completion scheduled for June 2030.

Swedish electrical infrastructure contractor Linjemontage has received a procurement award decision worth approximately SEK 1 billion from Svenska kraftnät for construction of a 400 kV overhead transmission line between Ekhyddan and Nybro in southeastern Sweden.

The proposed contract covers approximately 98 km of transmission infrastructure, connecting Ekhyddan in Oskarshamn municipality with Nybro. Linjemontage expects the project to commence towards the end of 2026 and reach completion in June 2030, although the procurement remains subject to a statutory ten-day standstill period before the agreement can be formally concluded.

Svenska kraftnät’s current development timetable anticipates construction beginning in 2027 at the earliest, with energisation targeted for 2030. The contractor’s anticipated commencement date therefore precedes the expected start of physical construction.

The transmission operator first applied to the Swedish Energy Markets Inspectorate for a network concession in June 2017. Following an extended permitting and appeals process, the concession became legally effective on 27 November 2025, exactly one year before Linjemontage received the procurement decision.

Preparations have included consultations with affected landowners and further assessment of individual sections of the proposed route. The development has also been designated a European Project of Common Interest, reflecting its contribution to the interconnected electricity system beyond Sweden’s domestic transmission requirements.

Southeastern Sweden accommodates substantial electricity flows associated with generation within the region and international connections, including NordBalt, the submarine electricity interconnector linking Nybro with Klaipėda in Lithuania.

NordBalt has a transmission capacity of 700 MW. Its operation increases the importance of the Swedish transmission infrastructure through which electricity imported from Lithuania can reach domestic consumers, or through which Swedish generation can be exported when electricity flows in the opposite direction.

The capacity of those domestic transmission routes influences how effectively the interconnector can operate under different system conditions. A restriction within Sweden’s network can constrain international electricity exchanges even when the submarine cable and its associated converter stations remain technically available.

Svenska kraftnät has identified the need for an additional transmission route around Nybro to accommodate increased electricity flows and reduce the risk that an equipment failure develops into a more extensive interruption.

Providing a second electrical path allows power to redistribute when an existing circuit becomes unavailable. However, the remaining circuits must have sufficient thermal capacity and operate within acceptable voltage and stability limits after that redistribution.

Transmission planning therefore considers the network’s behaviour following credible equipment failures alongside the electricity flows expected during normal operation. Restrictions arising from those assessments can reduce the amount of power that operators permit to move between regions, even when all transmission assets are initially available.

The Ekhyddan–Nybro development forms part of a wider reinforcement programme that also includes a proposed 400 kV overhead line between Nybro and Hemsjö, in Olofström municipality. Together, the projects are intended to strengthen the electricity transmission corridor extending towards southern Sweden.

Additional circuit capacity will also improve opportunities for work on the existing transmission network. Replacing ageing conductors, refurbishing substations, or carrying out other substantial interventions can require individual assets to remain unavailable for prolonged periods. Sufficient alternative transmission capacity allows operators to accommodate those outages without imposing equivalent restrictions on electricity transfers.

Delivering the new line will involve the installation of supporting structures, foundations, conductors, insulators, and earthing infrastructure across a route extending almost 100 km. The detailed engineering must account for differences in terrain, environmental conditions, access requirements, and mechanical loading along the corridor.

At 400 kV, the electrical clearances between conductors, supporting structures, and surrounding objects also influence tower design and the dimensions of the transmission corridor. Those clearances must accommodate changes in conductor position caused by wind loading and thermal expansion as electricity flows increase.

The new circuit will require integration with the associated substations, including switching and protection arrangements that enable the equipment to be isolated for maintenance or disconnected rapidly following a fault. Adding a transmission path can change the fault currents encountered elsewhere in the network, requiring coordination with existing protective equipment.

Comparable reinforcement requirements are driving expenditure across other European electricity networks, including the construction of additional British transmission infrastructure as network operators prepare to accommodate changing patterns of generation and demand.

Linjemontage’s procurement selection establishes the proposed construction contractor for the Ekhyddan–Nybro reinforcement. Subject to formal conclusion of the agreement, detailed preparations will progress towards construction and the targeted completion of the new transmission line in 2030.


  • Saxony approves 2.8 GWh battery development

    Saxony approves 2.8 GWh battery development

    Saxony has approved construction of a major battery storage installation. The 700 MW Wegefarth development will provide approximately 2.8 GWh of energy storage, with two construction phases and a dedicated 380 kV transmission connection.


  • Linjemontage selected for SEK 1bn transmission project

    Linjemontage selected for SEK 1bn transmission project

    Linjemontage has been selected for a Swedish transmission construction project. Svenska kraftnät’s procurement covers approximately 98 km of new 400 kV overhead infrastructure between Ekhyddan and Nybro, with completion targeted for 2030.