Britain has launched funding for ultra-long-duration electricity storage technologies nationwide. The £28m programme targets systems capable of supplying electricity for more than 100 hours, including advanced electrochemical storage and underground hydrogen technologies.
Government approval clears Beacon Fen solar and battery development plans. The Lincolnshire DCO covers 400MW of photovoltaics, up to 600MVA of battery storage, an on-site substation, and electrical connections operating at up to 400kV.
A cyberattack reportedly shut a small UK gas peaker temporarily. The unidentified roughly 15MW facility was offline for four days, while government and NCSC work on broader energy-sector cyber resilience continues.
Halenbeck-Rohlsdorf II has entered operation with 114MWp solar capacity installed. The Brandenburg plant is expected to generate up to 120GWh annually, with long-term PPAs covering Shell Energy Europe and two Finanz Informatik companies.
Kozloduy reduced Unit 5 output as Danube levels kept falling. The approximately 120MW preventative reduction responds to critically low river conditions and is the first such meteorological and hydrological measure in the plant’s 52-year operating history.
GEN-I has started construction of its Gheorgheni battery storage project. The 55MW/220MWh standalone system will connect through a 110kV, 63MVA substation, with WALDEVAR Energy delivering the EPC package and associated grid-connection works.
Capital Dynamics has acquired a 170MW four-hour Irish battery project. The ready-to-build Knockanure scheme has secured 170MW of grid capacity at the neighbouring 110kV substation, with procurement and delivery planning already under way.
Statkraft proposes replacing Høyanger hydropower with higher-capacity flexible plant assets. The two new stations would raise combined capacity from around 109MW to 257MW while using the same regulated water resources and existing reservoir limits.
Van Oord has completed all 111 Baltica 2 offshore monopiles. The campaign installed 107 turbine foundations and four offshore-substation foundations for the 1.5GW Polish project, clearing a major dependency for turbine, cable, and substation installation.
France has cleared preparatory works for EDF’s Gravelines EPR2 project. The environmental authorisation covers site infrastructure, earthworks, ground reinforcement, initial civil engineering, and cooling-water works while later nuclear installation approvals remain separate.