IN Brief:
- France has authorised preparatory works associated with two planned EPR2 units at Gravelines.
- The scope includes construction infrastructure, earthworks, ground reinforcement, rail changes, and initial civil engineering.
- EDF previously indicated that preparatory works are intended to begin in October 2026, while separate nuclear approvals remain ahead.
EDF has received environmental authorisation for the preparatory works required to develop two EPR2 nuclear units at Gravelines, allowing a substantial programme of site enabling and civil engineering to move forward before the separate approvals needed for the nuclear installations themselves.
Decree No. 2026-807, dated 20 August and published on 22 August, applies to works across Gravelines, Loon-Plage, Craywick, and Bourbourg. The authorised scope includes ecological relocation measures, servicing of construction platforms, temporary site installations, relocation of the existing rail terminal serving the nuclear site, new construction access, parking, earthworks, ground reinforcement, initial civil engineering, and creation of the future cooling-water intake channel.
The decree is an important project milestone, but it is not an authorisation to construct or operate the two reactors. France’s licensing process separates these enabling and environmental works from the later nuclear installation approvals, leaving further regulatory decisions ahead before the EPR2 units can progress through full construction and commissioning.
EDF submitted its environmental authorisation application on 23 October 2025. A public inquiry ran from 14 April to 15 May 2026, with the inquiry commission issuing its conclusions in June, before the government completed the authorisation process in August.
The ground-engineering package is particularly significant at Gravelines. EDF has identified soil reinforcement as one of the principal preparatory operations because the geotechnical design must account for settlement and the potential for soil liquefaction under severe seismic conditions. The solutions under consideration include treatment of the existing ground, replacement fill, and rigid inclusions, with detailed nuclear-safety assessment continuing separately.
EDF has previously said preparatory works at Gravelines are intended to begin in October 2026. With the environmental authorisation now in place, the project can move towards that mobilisation date while detailed conditions attached to the decree, environmental monitoring, and the remaining regulatory programme continue to shape how the work is carried out.
The challenge is complicated by the fact that Gravelines is not a greenfield energy site. The existing station operates six 900MWe pressurised water reactors and produced 32.27TWh in 2025, making it one of the most important generating sites in the French system. Construction activity therefore has to be organised around an operating nuclear facility with established safety, security, access, and logistics requirements.
That places unusual weight on sequencing. Heavy earthmoving, rail changes, ground reinforcement, construction compounds, water-management infrastructure, temporary electrical supplies, and contractor movements all have to be introduced without compromising the existing site’s operation. The preparatory phase is consequently doing more than clearing land: it is creating the physical and logistical conditions in which a multi-year nuclear construction programme can coexist with six operating units.
The rail-terminal relocation illustrates the scale of that preparation. Nuclear projects require large flows of concrete, steel, mechanical equipment, prefabricated components, and heavy plant over long periods, while some later components will impose transport constraints that conventional road logistics cannot easily absorb. Establishing reliable construction logistics early is therefore closely tied to productivity once the main civil works begin.
Ground reinforcement has a similar relationship with the later programme. Any uncertainty over settlement, bearing capacity, or seismic behaviour below the future plant block can become disproportionately expensive if it is discovered after major structures are under construction. Resolving those conditions during the enabling phase reduces the risk that reactor-building work is forced to stop while fundamental civil assumptions are revisited.
Gravelines is the second site in EDF’s initial six-reactor EPR2 programme, after Penly and before Bugey. The programme is intended to use a more standardised reactor design and a more industrialised construction approach than earlier French EPR projects, but standardisation does not remove site-specific engineering. Cooling arrangements, geology, transport routes, grid interfaces, environmental constraints, and the configuration of existing infrastructure remain different at each location.
Penly provides an indication of what the preparatory phase can involve once authorisation is secured. EDF’s work there has included major excavation, coastal protection, logistics platforms, construction access, temporary buildings, and a dedicated electrical supply for the site. Gravelines will follow its own design and sequencing, but the same principle applies: much of the schedule risk is created or removed before the reactor buildings become the most visible part of the project.
The latest decree therefore moves Gravelines into a more tangible delivery phase without pretending that the regulatory process is finished. EDF now has authority for a defined package of enabling works, while the nuclear licensing, detailed design, procurement, and eventual investment decisions remain separate gates.
For a programme measured in decades, that may look like an incremental step. In engineering terms it is the point at which the site starts being reshaped for the reactors that are intended to follow — and where assumptions about ground conditions, logistics, environmental controls, and construction interfaces begin to meet physical reality.


