IN Brief:
- All 62 turbines have been installed at the Dieppe-Le Tréport offshore wind farm following a six-month installation campaign.
- The development has been supplying electricity to France's transmission network since July 2026.
- Its grid connection incorporates two 225 kV submarine circuits and onshore transformation to 400 kV at Penly.
Offshore renewable energy developer Ocean Winds has completed installation of all 62 turbines at the Dieppe-Le Tréport offshore wind farm in northern France, bringing the approximately 500 MW generating development towards full operation.
The final turbine was installed following a six-month offshore construction campaign that began in June. The development started exporting electricity in July, with additional generating units progressively connected to the electrical infrastructure as installation advanced.
Located off the Normandy coast, the wind farm is being developed by Éoliennes en Mer Dieppe Le Tréport, a consortium involving Ocean Winds, Sumitomo Corporation, and Banque des Territoires. Ocean Winds is jointly owned by EDP Renewables and Engie.
Marine construction contractor Jan De Nul undertook the turbine installation campaign using its Vole au Vent installation vessel. The Siemens Gamesa turbines are mounted on jacket foundations, the first of which was installed in September 2025.
Completion of the installation campaign establishes the full physical generating fleet at the site. Ocean Winds expects the development to reach full power in the coming weeks, following the remaining activities required to bring all turbines into operation.
The wind farm’s progressive electricity production has been enabled by the completion of transmission infrastructure connecting the offshore generating installation to France’s onshore network.
French transmission system operator RTE’s connection programme incorporates two 225 kV submarine electricity circuits, extending approximately 23 km between the offshore substation and the coast. A further approximately three kilometres of underground infrastructure connect the cable landing point at Penly with the onshore substation.
At that facility, electrical infrastructure constructed by Eiffage’s Dorsalys business transforms the incoming 225 kV supply to 400 kV for connection to France’s national transmission network.
Increasing the transmission voltage reduces the current required to transport a given quantity of electrical power, limiting the resistive losses associated with moving electricity through the export circuits and into the wider network.
Submarine alternating current cables introduce additional electrical considerations because their capacitance creates charging currents while they remain energised. Those currents occupy part of the cable’s available electrical capacity, including during periods when relatively little active power is being exported from the wind farm.
The voltage control and reactive power requirements associated with the export connection must consequently be assessed across the development’s operating range. Changes in the number of generating turbines connected to the offshore collection network can alter those operating conditions as commissioning progresses.
Completing the mechanical installation of the turbines does not independently establish that the wind farm can deliver its entire rated generating capacity. Each turbine must be connected to the relevant collection circuits, with its electrical protection, communications, and control arrangements available before it can export electricity.
Individual generating units must also operate in coordination with the wider wind farm control system. The combined electrical behaviour of the installation at its transmission connection influences compliance with requirements covering active power control, reactive power provision, voltage regulation, and response to disturbances within the electricity network.
Progressive energisation can allow electricity production to begin while construction remains underway at other turbine locations. That approach requires clear management of the boundaries between operational electrical infrastructure and sections of the development where installation or testing activities continue.
The relationship between export infrastructure and generating availability was recently demonstrated at RWE’s Sofia offshore wind farm, where damage to an onshore electrical cable interrupted electricity production during the commissioning programme.
Dieppe-Le Tréport’s connection to the transmission network at Penly also brings offshore renewable generation into an area already associated with substantial electricity infrastructure serving the nearby nuclear power station. The resulting electricity flows must be accommodated within the operating limits of the surrounding transmission system.
Ocean Winds has achieved several further construction and operating milestones across its French generating portfolio during 2026. Its Îles d’Yeu et de Noirmoutier offshore wind farm entered full operation earlier in the year, while the Éoliennes Flottantes du Golfe du Lion floating wind development delivered its first electricity.
Those developments incorporate different offshore engineering configurations. Fixed-bottom installations such as Dieppe-Le Tréport transfer turbine loads through foundations anchored to the seabed, whereas floating developments require mooring systems and electrical connections capable of accommodating movement of the generating platforms.
The differences extend to installation and maintenance planning, particularly where electrical cables must tolerate repeated mechanical loading associated with the movement of floating structures.
With all 62 turbines now installed at Dieppe-Le Tréport, the project’s remaining commissioning activities will bring its full generating fleet into service. The completed export connection will then accommodate the development’s electricity production alongside the other generating assets connected to France’s high-voltage transmission network.