Saxony approves 2.8 GWh battery development

Saxony approves 2.8 GWh battery development

Saxony has approved construction of a major battery storage installation. The 700 MW Wegefarth development will provide approximately 2.8 GWh of energy storage, with two construction phases and a dedicated 380 kV transmission connection.


IN Brief:

  • CI V Gigastar ProjectCo has secured planning approval for a 700 MW battery storage development near Freiberg.
  • Construction will be divided into two phases providing 500 MW and 200 MW of power capacity respectively.
  • A new substation and underground 380 kV cable will connect the installation to the existing Freiberg Nord transmission substation.

The Saxony State Directorate has granted planning approval for a 700 MW battery energy storage development at Wegefarth in eastern Germany, where CI V Gigastar ProjectCo plans to install approximately 2,800 MWh of storage capacity.

Located in the municipality of Oberschöna near Freiberg, the development will be constructed in two phases, providing 500 MW and 200 MW of electrical power capacity respectively. Its associated infrastructure includes a new substation and an underground 380 kV cable connection to the existing Freiberg Nord transmission substation.

The decision, announced on 26 November, follows a formal planning procedure assessing the construction and operation of the storage facility and its associated electrical infrastructure. The approval documentation is scheduled to become publicly accessible today for a two-week period.

A separate environmental permitting decision concerning the project’s 380 kV substation was previously issued by the Mittelsachsen district authority, establishing the regulatory basis for construction and operation of that element of the development.

With its proposed 2,800 MWh energy capacity, the completed Wegefarth installation would have a nominal discharge duration of four hours at maximum rated power. Its usable output will depend on the battery systems’ permitted operating limits, conversion efficiency, and the capacity available through the grid connection.

The staged construction programme divides the development into two substantial electrical installations. Their delivery will require coordination between battery equipment procurement, power conversion systems, internal collection circuits, and construction of the transmission interface.

Each phase could involve separate commissioning activities, although the developer has not established publicly whether the first 500 MW of capacity will enter commercial operation before completion of the subsequent 200 MW installation.

Connecting at 380 kV places Wegefarth within Germany’s highest-voltage alternating current transmission network. At a power rating of 700 MW, the installation could represent one of the larger individual electrical loads connected to the surrounding infrastructure during charging periods, as well as a substantial source of electricity during discharge.

The power conversion equipment must manage those bidirectional electricity flows while maintaining the electrical characteristics required at the transmission connection. Battery modules store energy using direct current, with inverters providing the controlled conversion between their operating voltage and the alternating current collection network.

Individual converter outputs can be combined through medium-voltage circuits before transformation to 380 kV. Supervisory controls must coordinate the availability and output of the installed equipment, accounting for differences in state of charge, thermal conditions, and operating restrictions across individual battery units.

A transmission connection also requires protection systems capable of responding to faults affecting both the storage facility and the surrounding network. The electrical characteristics of converter-based installations differ from those of conventional synchronous generators, influencing how their fault behaviour must be represented in protection and system studies.

The proposed four-hour storage duration gives Wegefarth a different operating profile from several other German battery developments currently entering construction and commissioning. At Dahlem, for example, Kyon Energy has begun technical commissioning of a 100 MW/203 MWh battery, providing a nominal discharge duration of approximately two hours.

Longer discharge durations allow storage installations to sustain a particular output over more extended periods, potentially accommodating a larger proportion of the evening electricity demand that follows the decline in daytime photovoltaic generation.

That additional energy capacity also increases the quantity of electricity required to recharge the installation. After a substantial discharge, Wegefarth’s ability to replenish its stored energy will depend on the available import capacity, electricity prices, and the time remaining before its next anticipated dispatch.

Germany’s continued expansion of photovoltaic and wind generation provides potential opportunities for storage operators to charge during periods when electricity is abundant and return it to the network during periods of comparatively limited generation.

Storage can also contribute to managing congestion where its location and operating schedule correspond with the requirements of the affected network. A battery charging in a region with excess generation may reduce the volume of electricity that must be exported through constrained transmission circuits. Discharging at an unsuitable time could produce the opposite effect.

Operating strategies must therefore consider network conditions alongside commercial electricity market opportunities. The amount of energy available for wholesale trading may also be influenced by commitments to provide balancing services or other reserve capacity.

At Wegefarth, the proposed transmission connection establishes the electrical interface through which those services could eventually be delivered. The planning decision authorises the construction of the facility but does not establish the date of commercial operation, the installed battery chemistry, or the contractual arrangements through which its capacity will be marketed.

The next stages of delivery will include finalising the equipment specifications and implementing the electrical infrastructure required to bring the development’s planned 500 MW and 200 MW phases into service.


  • Saxony approves 2.8 GWh battery development

    Saxony approves 2.8 GWh battery development

    Saxony has approved construction of a major battery storage installation. The 700 MW Wegefarth development will provide approximately 2.8 GWh of energy storage, with two construction phases and a dedicated 380 kV transmission connection.