IN Brief:
- October balancing expenditure exceeded NESO's £455 million performance benchmark by 64%.
- Approximately 1.99 TWh of wind generation was curtailed during October as transmission constraints restricted electricity transfers.
- NESO's latest reported performance figures put cumulative balancing expenditure at £2.707 billion between April and October.
Britain’s electricity balancing costs reached a record £745 million in October, according to the latest performance figures published by the National Energy System Operator (NESO). The expenditure exceeded its benchmark for the month by 64%, as transmission constraints, network outages, and higher replacement generation costs increased the financial burden of operating the electricity system.
NESO’s latest reported metrics, published on 23 November, put cumulative balancing expenditure at £2.707 billion between April and October, against a benchmark of £2.272 billion. October’s expenditure exceeded the previous monthly record of £553 million established in September, with the system operator identifying sustained network congestion rather than a single exceptional event as a principal driver of the increase.
The performance figures follow NESO’s earlier October Balancing Services Use of System (BSUoS) outturn report, which estimated monthly balancing costs at £740.4 million. The two reports use different accounting and reporting treatments, with the performance series incorporating electricity system restoration costs and subsequent reconciliation of historical figures. NESO excludes winter contingency costs from its benchmark comparison.
The latest expenditure figures come amid reports that the Treasury has made an additional £1 billion of financing available to NESO. The Telegraph reported the financing arrangement on 20 November, attributing the additional borrowing requirement to the increase in balancing expenditure. NESO told the newspaper that the borrowing did not reflect its underlying financial position.
The system operator recovers balancing expenditure through fixed BSUoS tariffs, which have been in operation since April 2023. Establishing charges in advance provides electricity market participants with greater certainty over their expenditure. However, where actual operating costs exceed the forecasts used to determine those charges, a difference can develop between the amount collected and the expenditure incurred.
October’s earlier BSUoS outturn report illustrates the extent of that difference. Including NESO’s estimated internal costs, total BSUoS expenditure reached £808.15 million, corresponding to an estimated monthly charge of £35.68/MWh. That compares with the £16.25/MWh forecast used during tariff setting. The estimated outturn charge represents the cost of the month’s activities rather than an immediate replacement of the fixed tariff paid by electricity market participants.
Network congestion was particularly significant during October. NESO identified approximately 1,991 GWh of wind curtailment, with restricted transmission capacity limiting the amount of electricity that could be transferred from generating regions into areas of higher demand. Outages affecting Scotland’s B2 transmission boundary reduced available capacity to around 48%, while outages in the Midlands created additional limitations.
When those constraints prevent electricity from reaching consumers, NESO must adjust generation or consumption to maintain the safe operation of the network. Reducing output in one region can require additional generation elsewhere, depending on the prevailing balance between electricity supply and demand. The resulting expenditure reflects the commercial cost of modifying the operation of participating electricity assets.
Higher fuel and wholesale electricity prices increased that expenditure during October. NESO reported that day-ahead wholesale prices averaged approximately £145/MWh, while gas prices were substantially higher than a year earlier. The increase raised the cost of obtaining replacement electricity from gas-fired generation when transmission constraints prevented available wind output from being transported to consumers.
Transmission constraints nevertheless represent only part of the expenditure associated with electricity balancing. NESO must also procure services supporting frequency, voltage, operating reserves, stability, and electricity system restoration. Its annual figures put total balancing expenditure at £3.1 billion during 2025/26, including approximately £2 billion associated specifically with thermal transmission constraints.
Further expenditure is anticipated as network operators reinforce the infrastructure required to accommodate changing generation patterns. Earlier this month, NESO projected thermal constraint costs of £3.9 billion in 2027, reflecting continued network limitations and expectations of elevated gas prices.
The relationship between network reinforcement and operational costs is complicated by the outages required to undertake construction. Temporarily removing circuits from service can restrict electricity transfers before the additional capacity provided by completed infrastructure becomes available. Coordinating reinforcement programmes with generation availability and demand is therefore important to managing both near-term expenditure and longer-term network performance.
NESO is also examining measures that can increase the utilisation of existing transmission equipment, including dynamic line rating. By accounting for actual operating and environmental conditions, such systems can make additional electrical capacity available where equipment ratings and network security requirements permit. Their contribution will depend on the locations and characteristics of the constraints affecting the network.
The October figures demonstrate the financial consequences of the continuing disparity between available electricity generation and transmission capacity. Additional financing can address the timing of NESO’s expenditure and cost recovery, but reducing the underlying balancing requirement will depend on the delivery of network infrastructure and improvements to the operation of Britain’s electricity system.