IN Brief:
- Two ±150MVAr STATCOM installations have been completed at Sibiu Sud and Bradu.
- The approximately RON260 million project was delivered for Transelectrica with Siemens Energy.
- Dynamic reactive-power control will support voltage regulation, stability, and renewable integration.
Electromontaj has completed Romania’s first two transmission-network STATCOM installations, delivering ±150MVAr systems at the Sibiu Sud and Bradu substations for national transmission operator Transelectrica.
The approximately RON260 million programme was carried out by Electromontaj in association with Siemens Energy and has been completed around 12 months ahead of the deadline associated with its European financing. About RON254 million of the investment is supported through Romania’s allocation from the Modernisation Fund.
The installations provide dynamic reactive-power compensation and continuous voltage regulation at transmission level, allowing the system to respond rapidly as demand, renewable output, and inter-regional power flows change the electrical conditions across the network.
A static synchronous compensator, or STATCOM, uses power electronics to exchange reactive power with an alternating-current network. Its main role is not to transfer net electrical energy from generation to consumers but to influence voltage and system behaviour by adjusting reactive current in response to changing conditions.
That capability becomes increasingly valuable where power-system conditions can change quickly. Wind and photovoltaic plants connect through power-electronic interfaces and have operating characteristics different from the large synchronous machines around which much of Europe’s transmission infrastructure was originally developed.
Changes in generation mix therefore affect more than the amount of electricity available. They can alter where reactive power is supplied, the short-circuit strength available at different nodes, and the behaviour of voltage across transmission corridors, forcing operators to provide some system-support functions through dedicated equipment.
The Sibiu Sud and Bradu installations each provide a ±150MVAr operating range, allowing the equipment to either supply or absorb reactive power. That flexibility distinguishes a STATCOM from fixed compensation equipment designed primarily for one operating condition.
Shunt reactors, for example, can absorb reactive power where voltage tends to rise, while capacitor banks can provide support where additional reactive power is required. A STATCOM can move electronically across its operating range, giving the network a faster and more continuously controllable response.
Response speed is particularly relevant during disturbances or sudden changes in transfers. Power-electronic converters can alter output rapidly, allowing voltage support to be adjusted on timescales suited to dynamic system operation rather than waiting for slower mechanical switching or changes in generator dispatch.
Electromontaj also identifies damping of power oscillations within the interconnected European network as one of the intended functions. Oscillations can arise when groups of generators or network areas move electrically against one another following disturbances, and appropriately controlled power-electronic equipment can help suppress those movements.
The programme has moved into operation in stages. Sibiu Sud entered service in December 2025 as Romania’s first transmission-network STATCOM, while the Bradu installation was energised in May 2026. Completion of the overall contract now follows those individual commissioning milestones.
Sibiu Sud has an additional engineering distinction because the STATCOM is integrated at 37kV. The transformer station consequently operates across five voltage levels — 400kV, 220kV, 110kV, 37kV, and 20kV — adding another electrical interface to an already complex transmission node.
Using an intermediate voltage for a STATCOM allows the converter equipment to operate below the highest transmission voltage while a coupling transformer provides the interface with the EHV network. That architecture still requires substantial high-voltage engineering around transformers, switchgear, protection, cooling, auxiliary supplies, communications, and control.
Harmonic performance is another design consideration because power-electronic converters switch at high frequencies and can introduce waveform distortion if not properly engineered. Filters, converter controls, transformer characteristics, and network studies have to ensure the installation complies with system requirements across its operating range.
Protection is equally important. The equipment must remain available during permitted voltage variations while responding predictably to faults, and its controls have to coordinate with wider substation and transmission-system protection rather than acting independently on purely local measurements.
For Transelectrica, the STATCOMs add controllable resources to a voltage-management toolkit that already includes transformer tap changers, reactors, capacitors, network switching, and reactive capability from connected generators. Their main value lies in providing fast response where slower or less flexible measures may not be sufficient.
Romania’s summer 2026 system studies were already modelling the Sibiu Sud and Bradu units as available voltage-control resources, placing the installations inside practical transmission planning rather than leaving them as demonstration technology.
The project also illustrates the breadth of skills now involved in network reinforcement. STATCOM delivery combines civil construction, extra-high-voltage engineering, power electronics, software, digital control, factory testing, site testing, and commissioning against performance requirements defined by the transmission system rather than by individual component operation alone.
Increasing renewable penetration is likely to push more European grid investment towards similar dynamic-support equipment. New circuits and transformers increase transfer capability, but those assets alone cannot guarantee acceptable voltage and stability across every operating condition.
Sibiu Sud and Bradu therefore address one of the less visible constraints of the energy transition. Romania has added two ±150MVAr electronically controlled resources at strategic transmission nodes, giving system operators another means of managing voltage as generation and power flows become less predictable.