Grid constraints drive third electricity margin notice

Grid constraints drive third electricity margin notice

Britain has experienced electricity margin notices on three consecutive days. The initial 3,180 MW reserve shortfall forecast for Thursday was reduced to 900 MW in the afternoon update.


IN Brief:

  • NESO issued electricity margin notices for demand periods on 24, 25, and 26 November.
  • The initial Thursday warning identified 2,680 MW of generation excluded from the available margin because of system constraints.
  • The afternoon update reduced the forecast shortfall to 900 MW for the period from 16:00 to 20:00 GMT.

Britain’s National Energy System Operator (NESO) issued electricity margin notices for three consecutive days this week, with its initial warning covering Thursday identifying 2,680 MW of generating capacity excluded from the available system margin because of transmission constraints.

The initial forecast, published late on Wednesday, showed a 3,180 MW shortfall against the operating reserve required for the period from 06:00 to 20:00 GMT on 26 November. NESO subsequently divided the notice into two periods as it reassessed generation availability, demand, and network conditions.

The morning period, covering 08:00 to midday, carried a forecast shortfall of 1,300 MW. The subsequent period, from midday to 20:00, initially carried a 2,790 MW shortfall. The morning notice was withdrawn at 11:11, while a further revision at 14:04 reduced the afternoon requirement to 900 MW between 16:00 and 20:00. At that point, the warning was confined to the evening demand period.

Thursday’s warnings followed the cancellation of earlier electricity margin notices covering Tuesday and Wednesday. The latest sequence has focused attention on the amount of generation that can contribute to operational reserves once the physical restrictions of the transmission system are taken into account.

An electricity margin notice is a request for additional available capacity. NESO holds an operating reserve above expected demand so that it can maintain the balance between electricity production and consumption when forecasts change or generating equipment becomes unavailable. A shortage against that reserve requirement does not mean that the same volume of consumer demand is expected to go unmet.

The notice can encourage generators to revise their availability or identify other actions through which market participants can make additional capacity accessible to the control room. NESO continues to use its other balancing mechanisms while the notice is in force, reassessing the required margin as forecasts and available resources change.

The 2,680 MW excluded from Thursday’s initial assessment demonstrates the difference between generating capacity available at individual power stations and the capacity that can contribute to electricity system requirements. A generator can be technically available while its additional output cannot be accommodated through the transmission circuits connecting its region to other parts of Britain.

Transmission limits account for equipment ratings, voltage conditions, and the requirement to keep the network within acceptable operating limits following credible failures. Increasing generation on one side of a constrained boundary can leave insufficient capacity to redirect power safely if a significant transmission circuit trips.

Britain’s geographical distribution of renewable generation has made the transfer of electricity from northern generating regions to demand centres further south increasingly important. When wind output exceeds the available transfer capacity, NESO can reduce generation behind a constrained boundary and procure replacement electricity from assets elsewhere. The cost of doing so depends on the prices offered by the affected generators and other market participants.

Separate performance figures published this week put October’s electricity balancing costs at £745 million. That monthly figure covers multiple balancing activities, rather than solely the cost of transmission constraints or actions associated with this week’s notices.

Increasing transmission capacity through additional circuits, substations, and high-voltage direct current links can reduce the restrictions preventing available generation from being delivered to other regions. The resulting changes to system operation depend on the capacity and topology of the completed network, as well as the geographical distribution of subsequent generating developments.

Storage can contribute to the management of these restrictions where its location and dispatch coincide with the relevant network requirements. A battery on the exporting side of a constrained boundary may absorb generation locally, while storage on the importing side may reduce the need for power to cross that boundary during periods of high demand. These functions depend on the available state of charge and electrical connection capacity at each location.

Interconnectors can also bring additional electricity into Britain, subject to available transfer capacity, regional market conditions, and operating requirements in connected electricity systems. Their contribution to reserve management varies with the circumstances of each demand period.

Thursday’s initial warning also specified a contingency requirement of 550 MW. This was a separate operating parameter from the forecast margin shortfall, reflecting the need to maintain sufficient resources to respond to unexpected changes in system conditions. The afternoon revision reduced the forecast shortfall to 900 MW, with transmission availability remaining an important constraint for subsequent winter demand periods.