IN Brief:
- More than 21 GW of solar inverter demand and 13 GW of storage inverter demand are exposed to restrictions between 2027 and 2030.
- The base case forecasts respective deployment reductions of 6% and 5% in Central and Eastern Europe.
- Equipment substitution could increase system costs by 2–10%, with additional installation and servicing requirements.
Wood Mackenzie forecasts that restrictions on high-risk inverter suppliers could reduce photovoltaic and battery storage installations across major Central and Eastern European markets between 2027 and 2030, with procurement costs and access to local technical services constraining the deployment of alternative equipment.
Research commissioned by trade association SolarPower Europe estimates that more than 21 GW of photovoltaic inverter demand and 13 GW of battery storage inverter demand will be exposed to restrictions affecting projects receiving European Union financing during the four-year period.
The consultancy’s base case forecasts an average 6% reduction in photovoltaic installations across major Central and Eastern European markets and a corresponding 5% reduction in battery storage deployments compared with its previous expectations. Across Europe, the projected decline is approximately 3% for each technology.
The European Commission introduced restrictions affecting high-risk inverters used in projects receiving EU institutional loans or direct European funding in April 2026, with the grandfathering period for affected projects ending on 1 November. Wood Mackenzie identifies Chinese-headquartered suppliers as affected by the high-risk designation, although the Commission had not publicly issued a comprehensive formal document setting out the April decision when the consultancy completed its assessment.
Chinese manufacturers accounted for more than 80% of Europe’s inverter shipments during 2025. Their market shares are particularly high in price-sensitive countries that also rely heavily on EU financing for renewable electricity and storage developments.
Wood Mackenzie’s research draws on discussions and survey responses from more than 30 stakeholders, including developers, equipment suppliers, distributors, and national solar industry associations. Approximately 14% of Europe’s photovoltaic projects and 10% of storage projects depend on EU loans or direct funding, with Romania, Czechia, and Bulgaria facing particularly pronounced exposure.
The manufacturing capacity available from suppliers outside the high-risk designation is projected to exceed 150 GW by the end of 2027. However, the study identifies differences between aggregate manufacturing capacity and equipment that can actually be procured, installed, commissioned, and maintained in individual national markets.
A replacement inverter must meet the electrical and communications specifications of the plant and comply with applicable national network connection requirements. Depending on the original design, changing suppliers can require revised engineering documentation, control integration, or changes to associated electrical equipment.
Those requirements are more difficult to address when the alternative manufacturer lacks an established local technical organisation. Stakeholders told Wood Mackenzie that building adequate sales and after-sales capabilities could take months or years in some Central and Eastern European markets, even where a supplier is already certified to sell its equipment.
Battery storage procurement faces an additional constraint because many systems are sold as integrated AC blocks. The battery and its bidirectional power conversion equipment are supplied together, with the manufacturer responsible for coordinating their operation within a common product architecture.
Separating those components can require a developer or engineering contractor to assume additional integration responsibilities. Battery management and converter controls must exchange operating information, including permitted charging and discharging limits, while supervisory systems coordinate the aggregate output of the installation.
A supplier change may also alter the division of warranty responsibilities. Where the battery and converter originate from different manufacturers, the commercial arrangements must establish which organisation is responsible when system performance falls below contractual requirements or a fault occurs across the equipment interface.
Wood Mackenzie estimates that changing inverter procurement could increase system-level costs by between 2% and 10%, rather than merely increasing the purchase price of individual converters. Some developers consulted indicated that even a 1–5% cost increase could undermine already narrow project margins.
The combination of altered equipment specifications and new servicing requirements adds pressure to a rapidly growing storage market. A recent Hungarian battery storage contract between Hanersun and Electrical One combines integrated battery and substation equipment with plans to establish European servicing capabilities, demonstrating how supply and subsequent technical support are being incorporated into regional procurement arrangements.
Wood Mackenzie also modelled a separate, more severe scenario in which restrictions extend to a comprehensive EU-wide prohibition on high-risk inverters. Under that hypothetical arrangement, projected installations through 2030 in Central and Eastern Europe would fall by more than 18% for photovoltaic capacity and 13% for storage, with EU-wide declines of 11% and 13% respectively.
The broader scenario remains distinct from the restrictions on EU-funded projects already in effect. Under the base case, deployment losses are concentrated in 2027, when alternative suppliers’ local distribution and technical service networks are expected to be least developed. Subsequent deployment will depend in part on how rapidly suppliers can establish those capabilities and meet the requirements of affected projects.