ESB Networks doubles Julianstown transformer capacity

ESB Networks doubles Julianstown transformer capacity

ESB Networks has completed Julianstown’s latest electrical substation capacity upgrade. Two 5MVA transformers were replaced by 10MVA units, increasing installed capacity from 10MVA to 20MVA and supporting future electricity demand in County Meath.


IN Brief:

  • ESB Networks has replaced two 5MVA transformers with two 10MVA units at Julianstown 38kV Station.
  • The upgrade increases aggregate installed transformer capacity from 10MVA to 20MVA, with additional capacity equivalent to demand from approximately 2,500 homes.
  • The completed works form part of ESB Networks' €13.4bn national electricity infrastructure investment programme under Price Review 6.

ESB Networks has completed an electricity infrastructure upgrade at Julianstown 38kV Station in County Meath, replacing two existing 5MVA transformers with 10MVA units. The work doubles the station's aggregate installed transformer capacity from 10MVA to 20MVA, providing additional capacity to support housing development, commercial activity and growing electricity demand across east Meath and the wider northeast of Ireland.

The completed project adds 10MVA of installed transformer capacity at an established network location. ESB Networks estimates that the additional capacity is equivalent to the electricity requirements of approximately 2,500 homes, including demand associated with the electrification of heating and transport.

Julianstown 38kV Station serves communities and businesses in a region where electricity requirements are expected to increase through new development and changing energy use. Reinforcing an existing station allows the network operator to provide additional transformer capacity using established electricity infrastructure.

The replacement involved two transformers of the same original rating. Each existing 5MVA unit has been replaced by a 10MVA transformer, increasing both the individual ratings and the combined installed capacity of the equipment.

The larger units provide greater apparent power capability at the transformer level, subject to their operating conditions and the ratings of connected infrastructure. That additional capability must be considered alongside the electrical equipment through which power reaches and leaves the station.

Transformer ratings are normally expressed in volt-amperes because they must account for both real and reactive power. A 10MVA rating describes an apparent power limit under specified operating conditions, rather than a guaranteed ability to deliver 10MW of real power in every electrical application.

The real power associated with a given apparent power depends on the power factor of the connected load. Electrical current, thermal conditions and other equipment limitations also affect how a transformer can be operated without exceeding its design limits.

Aggregate transformer capacity must also be distinguished from firm network capacity. The presence of two 10MVA units does not necessarily mean that the station can continuously supply a 20MVA load following the loss of either transformer or another network component.

Firm capacity depends on the station configuration, redundancy requirements, ratings of associated circuits and the network operator's standards for maintaining supply during faults or maintenance. ESB Networks has confirmed the increased installed rating but has not specified a revised firm capacity figure for Julianstown.

Installing higher-rated transformers can require changes elsewhere in the electrical installation. Existing cable connections, switchgear, protection systems and other equipment must remain suitable for the load currents and fault conditions associated with the modified station.

Protection coordination is particularly important because transformer replacements can change the electrical characteristics of the circuits. Equipment must respond appropriately to abnormal conditions while allowing normal power transfer within the permitted operating range.

Transformer cooling and insulation also influence equipment operation. Losses generated during power transfer produce heat, and the equipment must be designed to manage its thermal conditions while maintaining suitable insulation performance at the intended voltage and loading.

The Julianstown announcement does not provide detailed specifications for the new transformers, the station's switching arrangements or associated protection upgrades. The confirmed engineering outcome is the replacement of both units and the increase in installed transformer capacity.

Commissioning transformer replacements requires controlled electrical procedures before equipment is returned to service. Inspections and tests establish whether the installed transformers and their connections meet the applicable technical requirements, with energisation undertaken within the network operator's operating arrangements.

The project is reported as complete, meaning the upgraded equipment has moved beyond the construction stage identified for developments where installation or commissioning remains outstanding. ESB Networks has not disclosed the individual contract value or a detailed construction timetable for the work.

Additional demand in east Meath is being driven partly by housing and economic development. Electricity networks must accommodate new connections while maintaining acceptable operating conditions for existing consumers, particularly where demand increases around established substations.

Electrification introduces further changes to consumption patterns. Electric heating can increase demand during colder weather, while vehicle charging can produce substantial electrical loads depending on charging power, usage patterns and the extent to which demand is managed across different periods.

Electricity network planning therefore relies on the expected coincidence of loads rather than the sum of every connected device's maximum rating. Network engineers assess demand forecasts alongside the ratings and operating conditions of transformers, feeders and other assets to establish where additional capacity is required.

The estimate of demand equivalent to approximately 2,500 homes provides an indication of the upgrade's scale. It does not mean that the additional transformer capacity has been allocated exclusively to housing or that the same electrical demand applies to every household.

The completed works form part of ESB Networks' broader investment programme in northeastern Ireland, where infrastructure improvements are intended to support residential, commercial and community development. Other reinforcement projects will depend on local demand forecasts and the capacity available within the existing electricity system.

At national level, ESB Networks is undertaking a €13.4bn electricity network investment programme under Price Review 6. The programme is intended to strengthen and extend infrastructure as Ireland accommodates additional connections, increased electricity consumption and the adoption of technologies such as electric heating and transport.

The national investment figure covers a much wider range of projects than the Julianstown transformer replacements. It should not be interpreted as the cost of this individual substation upgrade, for which no separate expenditure figure has been disclosed.

With both transformers replaced, Julianstown 38kV Station now has 20MVA of installed transformer capacity. The completed reinforcement provides an increased equipment rating at an existing network location as ESB Networks prepares for further electricity demand growth across County Meath.


  • GE Vernova expands US transformer manufacturing

    GE Vernova expands US transformer manufacturing

    GE Vernova is expanding transformer manufacturing at its Shreveport factory. The $34.5m programme will increase production equipment and capacity, with 175 additional direct jobs projected and full production expected in 2028.


  • ESB Networks doubles Julianstown transformer capacity

    ESB Networks doubles Julianstown transformer capacity

    ESB Networks has completed Julianstown’s latest electrical substation capacity upgrade. Two 5MVA transformers were replaced by 10MVA units, increasing installed capacity from 10MVA to 20MVA and supporting future electricity demand in County Meath.