Energy Dome has advanced Ireland’s first commercial CO2 Battery project. The 23MW / 200MWh Offaly system will supply Google under a bilateral offtake arrangement.
European ministers have moved grid reforms into formal legislative talks. The package would reshape planning, permitting, congestion revenue, interconnection, and resilience rules across the EU.
GRIDSERVE’s charging network has reached a commercial scale milestone point. The company reported £64m of charging-network revenue in 2025, positive group EBITDA, 99% availability, and continued expansion across ultra-rapid bays and strategic road-network sites.
ContourGlobal has entered UK storage through a Scottish acquisition deal. The company has acquired the 500MW/2,000MWh Wallace BESS project in Ayr, adding a consented grid-scale storage asset with Gate 2 status to its portfolio.
Balfour Beatty has secured Netherton Hub’s main works package contract. The £325m two-year SSEN Transmission contract covers earthworks and civil infrastructure for two substations, three HVDC converter stations, an operations base, and associated facilities.
National Grid has energised another Hinkley Connection Project section milestone. The work brings 44km of overhead line between Sandford and Seabank into service, strengthening south-west transmission capacity as the wider 57km route moves toward completion.
Western Link 2 has entered its first public consultation phase. National Grid and SP Energy Networks are proposing a 2GW Scotland-Wales HVDC connection, combining offshore cable, underground cable, a new converter station, and Pentir substation works.
LionLink is moving further into formal investment and delivery planning. The hybrid DC interconnector would link Dutch offshore wind infrastructure with Dutch and UK onshore high-voltage systems, combining generation export and cross-border electricity exchange.
Elmed now moves into the practical converter-station delivery phase programme. The supplier will provide HVDC technology for the 600MW Italy-Tunisia link, including valves, controls, transformers, switchgear, studies, installation supervision, and commissioning.
NESO’s first summer margin notice exposed changing electricity adequacy risks. The warning was cancelled after sufficient capacity became available.