EIB signs €400m financing for Cernavodă refurbishment

EIB signs €400m financing for Cernavodă refurbishment

Nuclearelectrica has signed €400 million financing for Cernavodă’s reactor refurbishment. The European Investment Bank agreement supports equipment replacement, reactor retubing, and system upgrades intended to extend Unit 1’s operating life by 30 years.


IN Brief:

  • Nuclearelectrica signed a €400 million financing agreement with the European Investment Bank on 16 November 2026.
  • Unit 1's refurbishment includes reactor fuel-channel replacement, calandria tubes, feeder systems, and other nuclear and conventional equipment.
  • The €3.1 billion programme targets another 30 years of operation, with major refurbishment works planned from 2027.

Nuclearelectrica has signed a €400 million financing agreement with the European Investment Bank (EIB) for refurbishment of Unit 1 at Romania’s Cernavodă nuclear power station, advancing a major engineering programme intended to extend the reactor’s operating life by another 30 years.

The agreement was signed on 16 November and confirmed by the EIB on 17 November. It represents the first half of an €800 million financing package approved by the bank’s board in July 2026. A second €400 million agreement is expected in 2027, subject to the progress of the investment.

The refurbishment programme has an estimated investment cost of €3.1 billion, excluding financing costs. Nuclearelectrica is arranging additional funding through its own resources, export credit agencies, commercial lenders, and international financial institutions.

The EIB loan has a maturity of up to 22 years, providing long-term financing for an asset whose refurbishment is intended to support several decades of further electricity production. The signed agreement formalises the initial financing commitment rather than constituting approval for a new nuclear generating unit.

Cernavodă is located in southeastern Romania near the Black Sea and operates two CANDU 6 nuclear reactors. Unit 1 entered commercial operation in 1996, followed by Unit 2 in 2007. Together, the two units generate approximately 20% of Romania’s electricity.

Extending the life of Unit 1 requires replacement and refurbishment of components that have operated under demanding mechanical, thermal, and radiation conditions throughout the reactor’s first operating cycle. The programme includes work within the nuclear island and on supporting conventional generating equipment.

CANDU reactors use pressurised heavy water as the primary coolant and a separate heavy water system as the neutron moderator. Unlike a reactor with a single large pressure vessel containing the fuel assemblies, the CANDU design incorporates multiple horizontal fuel channels passing through the reactor vessel.

Each fuel channel contains components that allow coolant to circulate around the nuclear fuel while maintaining the required separation between the coolant and moderator systems. The channels operate under high temperature and pressure, and their condition is central to the safe operation of the reactor.

Reactor retubing involves replacing ageing fuel-channel components, including pressure tubes and calandria tubes, together with associated feeder systems. The refurbishment requires specialised tools, precisely controlled procedures, and extensive inspection records because these components form part of the reactor’s primary systems.

Pressure tubes contain the pressurised coolant flowing around the fuel, while calandria tubes provide part of the separation between the fuel channels and the moderator. The replacement programme must preserve the required geometry, material condition, and integrity of the assembled systems.

Feeder pipes connect the reactor’s fuel channels with the primary heat transport system, carrying coolant between the channels and associated equipment. Their replacement involves detailed engineering of connections, materials, and installation methods, followed by testing before the refurbished system can be returned to service.

Retubing is a substantial engineering undertaking because the components are located within the reactor structure and must be removed and replaced using carefully planned access arrangements. Equipment condition, installation tolerances, material traceability, and the sequence of work all influence the refurbishment programme.

The project also covers conventional plant equipment, including systems associated with converting reactor heat into electricity. The turbine-generator and its auxiliary equipment must be capable of supporting the intended operating period following refurbishment, alongside the upgraded nuclear systems.

Nuclearelectrica has awarded engineering and equipment contracts to an international supply chain. The principal engineering, procurement, and construction contract was signed in December 2024 with a consortium comprising Candu Energy, an AtkinsRéalis company, Ansaldo Nucleare, Canadian Commercial Corporation, and Korea Hydro & Nuclear Power.

The consortium’s work includes detailed engineering, equipment procurement, construction activities, and reactor refurbishment. Other specialist suppliers have responsibilities for conventional generating equipment, including work involving the turbine-generator.

Preparatory engineering has been progressing before the main reactor shutdown. The project includes procurement of components with long manufacturing lead times, development of refurbishment procedures, and preparation of infrastructure required to support specialist work on the reactor.

These activities are necessary because the principal refurbishment outage will involve several interconnected operations that must be completed before Unit 1 can return to service. Delays to a critical component, specialist tool, or installation activity can affect work elsewhere in the programme.

Civil construction began in September 2025 on infrastructure supporting the refurbishment, including facilities associated with handling and storing radioactive materials and maintaining specialist equipment used during reactor retubing.

The planned works therefore extend beyond replacement of components inside the reactor. Temporary and permanent infrastructure must support personnel, equipment handling, material movements, quality assurance, and the management of radioactive waste generated during refurbishment activities.

The major implementation phase is scheduled to begin in 2027 and take approximately three years. Unit 1 will be shut down for the principal refurbishment works, including retubing, equipment replacement, testing, and preparations for recommissioning.

Completion of construction and installation activities will not independently authorise the reactor’s return to service. The operator must demonstrate that the refurbished systems satisfy applicable nuclear safety requirements and obtain the regulatory permissions necessary for restart and continued operation.

Testing must establish the condition and performance of the replaced components, verify system integrity, and confirm that the equipment operates as required. The programme will also need to coordinate the recommissioning of conventional generating equipment with the reactor’s nuclear systems.

Nuclearelectrica expects the refurbishment to support a further 30 years of electricity production, although the extension remains conditional on successful completion and regulatory compliance. The company’s programme targets continued operation into the second half of the century.

The financing arrangements have developed alongside the engineering contracts. In July 2026, the EIB’s board approved €800 million in potential financing, and Nuclearelectrica’s shareholders subsequently authorised the proposed borrowing structure, divided into two successive agreements.

The 16 November signature establishes the first €400 million agreement as a contractual financing commitment. The remaining €400 million is expected to be formalised separately rather than being treated as already signed or drawn down.

Financial commitments and engineering delivery also operate on different schedules. The loan supports the refurbishment programme, but individual contracts, equipment deliveries, and construction activities will continue to be governed by their own requirements and milestones.

Cernavodă’s existing contribution to Romania’s electricity supply makes the timing of the refurbishment significant for generating capacity planning. Unit 1’s extended outage will remove its output from normal service while the refurbishment is undertaken, before the plant can resume production following the required approvals.

The project is designed to preserve existing nuclear generating capacity rather than increase the number of reactors at the site. Separate proposals for Cernavodă Units 3 and 4 remain distinct developments with their own financing and delivery arrangements.

The initial EIB financing agreement provides a further element of the financial structure required to deliver Unit 1’s refurbishment. Equipment procurement, site preparation, and engineering work will continue ahead of the planned main shutdown in 2027, followed by replacement activities and eventual recommissioning.


  • Fluke finds widespread UK data centre electrical disruption

    Fluke finds widespread UK data centre electrical disruption

    Fluke finds electrical reliability problems widespread across UK data centres. Its research found that 79% of respondents experienced electrical issues contributing to disruption or near-misses, while only 17% considered their infrastructure fully prepared for higher-density AI workloads.


  • Nefco provides €6.7m for Danish battery development

    Nefco provides €6.7m for Danish battery development

    Nefco has financed Danish battery developer BattMan’s expanding storage programme. The €6.7 million loan will fund project development and grid connection costs, supporting a portfolio exceeding 350 MW of capacity operational or under construction.