East Coast Cluster contracts exceed £2.25bn

East Coast Cluster contracts exceed £2.25bn

East Coast Cluster supply contracts have now exceeded £2.25 billion. The procurement milestone covers more than 350 agreements supporting Net Zero Teesside Power and the Northern Endurance Partnership’s associated carbon transportation and storage infrastructure.


IN Brief:

  • The value of UK supply chain contracts has increased from £1.5 billion in March 2026.
  • Net Zero Teesside Power is designed to provide up to 742 MW of dispatchable generating capacity.
  • Construction and operational preparations encompass electricity generation, carbon capture, compression, and transportation infrastructure.

Delivery partners for the East Coast Cluster have awarded more than £2.25 billion in supply chain contracts to UK businesses as construction progresses on the Net Zero Teesside Power generating station and associated carbon transportation and storage infrastructure.

The procurement figure, disclosed on 23 November, encompasses more than 350 contracts across Net Zero Teesside Power and the Northern Endurance Partnership (NEP). The combined value of UK contracts has increased from approximately £1.5 billion in March.

The developments are expected to create and support more than 3,000 jobs, with procurement spanning equipment manufacturing, construction, engineering, maintenance, and specialist industrial services.

Net Zero Teesside Power is being constructed at the former Redcar steelworks site. Its combined-cycle gas turbine generating station is designed to deliver up to 742 MW of dispatchable electricity while capturing up to two million tonnes of carbon dioxide annually for permanent storage beneath the North Sea.

Construction reached a major equipment delivery milestone in October with the arrival of the GE Vernova gas turbine. Technip Energies leads the engineering, procurement, and construction consortium, working alongside GE Vernova, Balfour Beatty, and Shell Catalysts & Technologies.

Integrating carbon capture into a combined-cycle generating station introduces additional engineering requirements at the interfaces between electricity generation and chemical processing equipment. A conventional combined-cycle installation recovers heat from gas turbine exhaust to generate steam, which drives a second turbine and increases the overall generating efficiency of the plant.

At Net Zero Teesside Power, exhaust treatment must additionally separate carbon dioxide from the gas stream. Solvent-based capture involves absorbing carbon dioxide into a liquid before applying heat to release the concentrated gas and regenerate the solvent for reuse.

Steam requirements for solvent regeneration, alongside the electrical consumption of pumps, compressors, and other auxiliary equipment, must be incorporated into the design of the generating station. The balance between electricity production and process energy consumption will influence its net output and efficiency across different operating conditions.

Compression prepares the captured carbon dioxide for transportation through the infrastructure developed by NEP. The generating station’s operating arrangements must consequently account for the availability and capacity of the downstream transportation and storage network.

Procurement for that network encompasses equipment that serves the wider industrial cluster rather than the generating installation alone. NEP’s infrastructure is intended to accommodate carbon dioxide from multiple industrial facilities, allowing participating projects to use common transportation and offshore storage arrangements.

The projects’ combined contract value reflects the breadth of those infrastructure requirements. Alongside electrical and mechanical equipment procurement, construction activities encompass process facilities, pipelines, civil engineering, and associated services.

Operational preparations have also been progressing alongside equipment deliveries. In March, px Group was appointed to provide operations, engineering, and maintenance services, with plans to establish an onsite workforce of approximately 100 people, including apprentices.

The maintenance arrangement will require personnel capable of managing the interaction between generating equipment and the associated process systems. Maintenance planning for a conventional power station already involves coordination of turbine inspections, electrical equipment outages, and the availability of auxiliary services. Integrating carbon capture adds further equipment dependencies.

An interruption to the capture or compression process could affect the operating capabilities available to the generating station even where its principal turbine equipment remains serviceable. Control and instrumentation systems must coordinate operating limits across the different facilities, while electrical protection must respond appropriately to faults affecting individual equipment items or their common supplies.

Flexible operation creates additional requirements for that integration. Gas-fired power stations can adjust electricity production in response to network demand, but changes in generating output also alter the volume and characteristics of exhaust gases reaching the capture equipment.

Process controls must accommodate those changes while maintaining acceptable operating conditions within the capture plant. The availability of steam for solvent regeneration and the operating limits of downstream compression equipment can also influence the overall response.

Britain’s electricity system is expected to require dispatchable generation alongside increasing volumes of wind and solar electricity, with the performance of integrated carbon capture installations depending partly on their ability to operate under changing demand conditions.

Net Zero Teesside Power is targeting start-up in 2028. The construction programme must now progress through further equipment deliveries, electrical and mechanical installation, and testing of the interfaces between the generating station and associated carbon management infrastructure. Demonstrating the integrated operation of those systems will be a central requirement before commercial generation can commence.


  • East Coast Cluster contracts exceed £2.25bn

    East Coast Cluster contracts exceed £2.25bn

    East Coast Cluster supply contracts have now exceeded £2.25 billion. The procurement milestone covers more than 350 agreements supporting Net Zero Teesside Power and the Northern Endurance Partnership’s associated carbon transportation and storage infrastructure.


  • Drax commits £120m to solar developments

    Drax commits £120m to solar developments

    Drax has committed £120 million to three northern solar developments. The projects represent approximately 130 MW of generating capacity and are supported by 15-year Contracts for Difference, with commercial operation expected in 2028.