Costain awarded Spennymoor 400 kV substation contract

Costain awarded Spennymoor 400 kV substation contract

Costain has won a £16.44m contract for Spennymoor substation works. National Grid plans a new customer generator bay, busbar extension, and associated protection modifications, with Stage Two construction conditional on a separate notice to proceed.


IN Brief:

  • National Grid Electricity Transmission published a £16.44m Spennymoor contract award notice naming Costain Limited on 20 November.
  • The proposed works include a 400 kV customer generator bay, MC4 busbar extension, and modification of Stella West 2 line-breaker protection arrangements.
  • The contract uses two-stage early contractor involvement, with construction subject to a separate notice to proceed after preparatory design and approval work.

Costain has been awarded a National Grid Electricity Transmission contract valued at £16.44m for work at the Spennymoor 400 kV substation in north-east England. A contract award notice published on 20 November identifies an extension to the existing installation to accommodate a new customer generator connection. The arrangement uses two-stage early contractor involvement: design and preparatory work proceed first, while the main construction stage remains subject to National Grid issuing a separate notice to proceed.

The scope includes extension of the MC4 busbar and a new customer generator bay owned by National Grid Electricity Transmission. It also specifies alterations to protection at the Stella West 2 line breaker, changing the connection from a feeder protection zone to a mesh corner protection zone. The work consequently affects both high-voltage switching equipment and the relays that determine which section of the system is isolated when a fault occurs. The notice does not identify the connecting generator’s technology or state an expected export date.

Spennymoor is an existing 400/132 kV air-insulated substation built around two single-switch mesh arrangements. The published procurement description lists four 400 kV lines — Stella West 1 and 2, and Norton 1 and 2 — alongside three 400/132 kV, 240 MVA supergrid transformers. Extending this arrangement requires the new connection to be integrated with the equipment already carrying power across the site. Electrical clearances, safe switching procedures and the protection scheme must all be considered before an additional bay can be energised.

Extending the busbar will create the required connection point within the substation, with the generator bay providing switching and protection for the incoming user. The protection design must establish which circuit breakers respond to faults, whether any existing relay zones need to change and how unaffected equipment remains in service. National Grid specifically calls for a Stella West 2 protection modification as part of that configuration. The task is therefore more involved than adding a single set of conductors to an existing high-voltage yard.

Civil work is included alongside the electrical installation. National Grid identifies compound extension and activities on adjacent non-operational land where the new customer bay will be located, with supply, installation, testing and commissioning obligations described in the notice. Foundations, access routes and safe working clearances must be incorporated into the final layout of an air-insulated switchyard. Work near existing live equipment also needs isolation planning, controlled access and coordination with the transmission operator’s operational requirements.

The notice names Costain Limited as the supplier and gives a contract value of £16,441,189 excluding VAT. Although publication took place on 20 November, the award itself is dated 3 November. The contract period is stated as 3 December 2026 to 27 December 2028, with provision for an extension to June 2029. These dates describe the procurement and planned delivery framework; they do not establish the start of construction or the date on which the customer’s connection will become operational.

Stage One of the early contractor involvement arrangement covers design development, investigations, planning, pricing and other pre-construction work. National Grid must then issue a notice to proceed before Stage Two construction is released, following agreement of the target cost and the required project approvals. Involving the contractor at the earlier stage allows buildability, equipment procurement and construction sequencing to influence the detailed design. The reported £16.44m contract value therefore covers an arrangement in which the full delivery phase is conditional rather than already under way.

The need to modify existing protection and busbar arrangements will affect the eventual construction sequence. New equipment must be installed and tested without compromising the protection of the four transmission circuits or the supergrid transformers already at Spennymoor. Planned outages, cable termination work, relay tests and commissioning of new switching equipment will have to be coordinated with National Grid’s operational procedures. The award notice identifies a defined generator-bay extension, not a replacement of the entire substation or the development of a new transmission line.

Costain’s immediate role is to prepare the engineering and commercial basis for National Grid’s second-stage decision. If that instruction is issued, construction and installation will follow, along with protection testing and commissioning before a generator connection can be energised. The public notice supplies the contract value, key work packages and planned dates, but the customer and generating technology remain undisclosed. Those details, together with any notice to proceed, will determine the next confirmed milestone at the Spennymoor site.


  • East Coast Cluster contracts exceed £2.25bn

    East Coast Cluster contracts exceed £2.25bn

    East Coast Cluster supply contracts have now exceeded £2.25 billion. The procurement milestone covers more than 350 agreements supporting Net Zero Teesside Power and the Northern Endurance Partnership’s associated carbon transportation and storage infrastructure.


  • Drax commits £120m to solar developments

    Drax commits £120m to solar developments

    Drax has committed £120 million to three northern solar developments. The projects represent approximately 130 MW of generating capacity and are supported by 15-year Contracts for Difference, with commercial operation expected in 2028.