Nexans wins 420km Greek interconnector cable subcontract

Nexans wins 420km Greek interconnector cable subcontract

Nexans will supply cable systems for Greece’s new island interconnection. Its subcontract covers 420km of mass-impregnated 110kV cable within the wider 1GW Corinth–Kos HVDC programme, with manufacturing activity expected to continue through mid-2028.


IN Brief:

  • Nexans has secured a 420km mass-impregnated 110kV cable subcontract from Hellenic Cables.
  • The wider Corinth–Kos development is rated at 1GW and 320kV and spans substantial subsea and land cable routes.
  • Nexans expects related manufacturing activity to occupy its MI production lines through mid-2028.

Nexans has won a subcontract to deliver 420km of mass-impregnated 110kV cable for the Corinth–Kos electricity interconnection in Greece. The French cable manufacturer will work for Hellenic Cables, which is delivering the project with Asso.subsea under an award from Greece’s Independent Power Transmission Operator, IPTO. The assignment forms part of a much larger 1GW, 320kV HVDC scheme intended to strengthen electricity connections between the mainland and the Dodecanese islands. Nexans confirmed the award on 6 November and has already begun preparatory project activity.

The Corinth–Kos development comprises approximately 1,260km of subsea cable and 30km of land cable across the wider programme. Nexans’ 420km assignment is one defined package within that project, with its own 110kV specification. IPTO gives the overall HVDC interconnection a rating of 1GW and 320kV; that system-level voltage must not be substituted for the rating of every individual cable supplied. Engineering drawings will determine the interfaces between the different voltage levels and equipment packages, while the contracting parties remain responsible for their respective delivery scopes.

Mass-impregnated insulation uses an impregnating compound within the cable’s dielectric structure. The technology has an established history in high-voltage submarine transmission, where insulation integrity and mechanical performance must be maintained through production, transportation, installation, and long-term service. The announced Nexans package does not yet disclose conductor dimensions, accessory specifications, or the arrangements at transitions to other equipment. Those details are important to manufacturing and testing because the cable’s electrical rating must be matched to its accessories, terminations, and operating environment.

Nexans said seabed survey activity and work on its mass-impregnated cable production lines had begun. The contract is expected to support manufacturing from the end of 2026 throughout 2027 and into the middle of 2028. That production horizon provides an indication of the planned industrial workload, although it is not a stated completion or energisation date for the entire interconnector. Subsea cable programmes typically require manufacturing coordination with route surveys, transportation, marine installation, jointing, and subsequent electrical testing, with each operation dependent on access to an appropriate work window.

The Corinth–Kos project is designed to bring the Dodecanese into a more interconnected electricity system. Island networks face particular challenges when their electricity supply depends on locally available generation and limited transfer capability. A mainland interconnection can create an additional route for importing and exporting electricity, subject to the capacity and operating arrangements of the completed infrastructure. The 1GW rating describes the planned transfer capability of the project, rather than output from a new generator.

Pascal Radue, executive vice-president of PWR-Transmission at Nexans, said the project reflected increased demand for high-voltage infrastructure between regions. The contract would support “significant activity across our manufacturing operations”, he said, as the group’s specialist lines work through the production programme. Nexans has not disclosed the subcontract value. Industrial capacity is part of the delivery challenge: high-voltage cable production occupies dedicated equipment for extended periods, and commissioning requirements determine when factory-produced lengths can be released for onward installation.

Hellenic Cables holds the principal award from IPTO in consortium with Asso.subsea, while Nexans is contracted to Hellenic Cables for its specified cable package. The consortium’s subsea delivery activity will have to coordinate with manufacturing schedules, vessel availability, route investigations, and installation conditions. A large programme can involve multiple manufacturers and contractors working to a common electrical design, with interfaces agreed before the individual systems are tested together. The project-wide subsea length therefore should not be attributed to Nexans as its own manufacturing commitment.

The manufacturing programme will need to align with cable-laying work across a long marine corridor. Route characterisation is necessary to identify seabed conditions, crossings, and installation constraints before final installation planning. Access to specialised vessels, the handling characteristics of each cable length, and suitable interfaces between segments will be practical delivery considerations. Nexans has confirmed a seabed survey is among the activities initiated, but it has not issued a separate statement that its entire contracted route has been surveyed or that offshore installation has begun.

IPTO’s development programme now has a further specialist cable supplier confirmed, with work scheduled through mid-2028 on Nexans’ manufacturing lines. Route surveys, marine operations, onshore connections, and electrical testing will need to be completed before the link can carry power between the mainland and the islands. Factory acceptance tests can establish whether a manufactured cable meets specified criteria, while installation and subsequent testing address different risks arising from transportation, jointing, and laying. The award gives greater definition to the equipment supply chain; an energisation date for the full interconnection has not been established in Nexans’ 6 November account.