Schiphol solar park resumes full operation

Schiphol solar park resumes full operation

A major Dutch solar park has resumed full electricity production. The 144 MWp development near Schiphol Airport has undergone extensive reconstruction using specially developed photovoltaic modules to address glare affecting approaching aircraft.


IN Brief:

  • Energy Solutions Group has restored its De Groene Energie Corridor solar park following the replacement of 228,696 photovoltaic modules.
  • The original installation generated glare affecting aircraft approaching Schiphol's Polderbaan and Zwanenburgbaan runways.
  • Replacement modules developed by LONGi have undergone independent testing against agreed aviation safety criteria.

Belgian renewable electricity producer Energy Solutions Group has restored its De Groene Energie Corridor solar park near Amsterdam Schiphol Airport to full operation, following an extensive reconstruction programme involving the replacement of 228,696 photovoltaic modules to address aviation safety concerns.

The 144 MWp installation occupies approximately 100 hectares beneath the approach routes to Schiphol’s Polderbaan and Zwanenburgbaan runways. Its anticipated annual electricity production is approximately 123 GWh.

Energy Solutions Group acquired the development in early 2024. Subsequent reports from pilots concerning reflected sunlight led Schiphol to restrict use of the Polderbaan runway during certain periods in March 2025, when the position of the sun created potentially hazardous glare.

The original environmental permitting arrangements had specified photovoltaic modules incorporating deeply textured glass to reduce reflections. However, the developer subsequently installed equipment using more lightly textured glass after the originally specified module type became unavailable.

Schiphol and airline KLM initiated legal proceedings in July 2025, with a court subsequently ordering the removal of approximately one-third of the installation’s photovoltaic modules. An agreement between the developer, Schiphol, the municipality of Haarlemmermeer, and the Dutch Ministry of Infrastructure and Water Management established a basis for addressing the problem across the development.

The initial remediation proposal involved removing the photovoltaic modules, applying anti-reflective film, and returning them to their original positions. The Dutch government committed €6.84 million towards the agreed intervention, with contributions also being made by other participating organisations.

Further technical and commercial assessments led to the selection of replacement modules developed by LONGi. Independent testing indicated that their reflection characteristics were superior to those of the previously proposed film treatment and met the safety criteria agreed between the participating organisations.

Reconstruction using the replacement equipment began in March 2026. Haarlemmermeer’s municipal authority reported that the final modules had been installed by the end of June, with the developer confirming the restoration of full operation on 27 November.

Photovoltaic modules convert incoming solar radiation into electricity but also reflect a proportion of that radiation from their protective front surfaces. The direction and intensity of reflected light depend on the optical characteristics of the module, its orientation, and the angle at which sunlight strikes it.

A smooth surface can produce a comparatively concentrated reflection in a particular direction. Texturing the front glass can redistribute that reflected light over a wider range of angles, reducing its intensity at individual observation points.

The effectiveness of such treatments depends on the surface characteristics and the geometry of the installation. A module that produces little problematic reflection under one set of conditions may behave differently when sunlight arrives at a lower angle.

At Schiphol, those conditions change throughout the day and across the seasons. The relevant observation points also move continuously as aircraft descend towards the runways, making the geometry of the approach paths an important component of the assessment.

The replacement modules must therefore satisfy optical requirements alongside their electrical performance specifications. Reducing concentrated reflections while maintaining light transmission to the photovoltaic cells allows the installation to generate electricity without recreating the conditions that prompted the runway restrictions.

The reconstruction also required the management of electrical interfaces between the replacement modules and the existing generating infrastructure. Photovoltaic modules are connected into strings, whose combined voltage and current must remain compatible with the operating ranges of the associated inverters and protection equipment.

Where replacement modules differ from those originally specified, their electrical characteristics must be assessed against the configuration of those strings. Temperature-related voltage variation, current ratings, and inverter input limits can influence the suitability of the replacement equipment.

Removing and reinstalling modules across a development of this size also creates extensive electrical testing and commissioning requirements. Individual photovoltaic modules can produce voltage whenever sufficient light is available, requiring appropriate isolation and installation procedures throughout the reconstruction programme.

Restoring the generating circuits involves verifying electrical connections, insulation integrity, and the operation of associated protective and power conversion equipment before electricity production resumes.

Haarlemmermeer’s municipal authority has identified the lack of a generally established Dutch or European glare standard for this application as a difficulty in resolving the original problem. The agreed project-specific assessment criteria provided a basis for evaluating the replacement modules before their installation.

At its anticipated production of 123 GWh annually, the reconstructed solar park would achieve approximately 854 equivalent full-load generating hours at its stated 144 MWp capacity. Actual electricity production will depend on solar irradiation, equipment performance, and operational availability following the completion of the remediation programme.


  • Schiphol solar park resumes full operation

    Schiphol solar park resumes full operation

    A major Dutch solar park has resumed full electricity production. The 144 MWp development near Schiphol Airport has undergone extensive reconstruction using specially developed photovoltaic modules to address glare affecting approaching aircraft.


  • Vestas secures 292.5 MW Romanian turbine contract

    Vestas secures 292.5 MW Romanian turbine contract

    Vestas will supply 45 turbines for Romania’s Dunarea East development. The 292.5 MW contract with Rezolv Energy includes installation, commissioning, and 15 years of servicing, with commercial operation targeted for early 2029.