IN Brief:
- Six three-phase 500kV shunt reactors weighing more than 120 tonnes each have reached HumeLink substations.
- The units will provide reactive-power compensation across the project's 500kV double-circuit transmission loop.
- Hitachi Energy is also installing 28 high-voltage circuit breakers, with final reactor commissioning expected by year-end.
Hitachi Energy has completed delivery of six three-phase 500kV shunt reactors for Transgrid’s HumeLink project in New South Wales, moving a major package of high-voltage equipment from manufacture and heavy transport into installation and commissioning.
Each reactor weighs more than 120 tonnes and will be installed across the Maragle, Bannaby, and Gugaa substations. Hitachi Energy says the units are among the first three-phase 500kV shunt reactors used in Australia and will provide reactive-power compensation within HumeLink’s 500kV double-circuit transmission loop.
The equipment performs a less visible role than towers and conductors but is fundamental to the electrical behaviour of a long high-voltage line. Transmission circuits generate reactive power because of their capacitance, particularly when lightly loaded, which can cause voltage to rise beyond acceptable limits if that reactive power is not controlled.
Shunt reactors absorb reactive power and help hold system voltage within its operating range. The requirement becomes increasingly significant on long high-voltage circuits because line charging current is present even when relatively little real power is being transferred.
HumeLink will run for approximately 365km and forms a major reinforcement of the New South Wales transmission system. A project of that scale has to be engineered around both the amount of real power it is expected to move and the voltage, reactive power, protection, and stability conditions that occur across different operating states.
The six reactors form part of the equipment needed to keep those conditions within limits. They will operate alongside transformers, switchgear, circuit breakers, protection systems, measuring equipment, communications, and network controls rather than as isolated components.
Hitachi Energy is also supplying and installing 28 high-voltage circuit breakers for HumeLink. The breakers provide another essential layer of the substation system, allowing circuits and major equipment to be switched and faults to be interrupted under the conditions for which the network has been designed.
The supplier’s service team is leading assembly, installation, and testing of all six reactors on site, supported by Australian subcontractors. Delivery therefore marks the end of the manufacturing and transport phase for these units rather than completion of the package.
Each reactor still has to be assembled, connected, tested, and integrated with protection and control systems before it can perform its intended role on the 500kV network. Commissioning will confirm insulation condition, electrical connections, protection settings, control interfaces, and response under the procedures specified for the substations.
The logistics demonstrate the physical scale of transmission equipment. The reactors were manufactured at Hitachi Energy’s Chongqing facility in China, shipped to Port Kembla south of Sydney, and moved by heavy-haul road convoy for approximately 480km to their destination substations.
Transporting electrical equipment weighing more than 120 tonnes requires detailed planning around vehicle configuration, bridges, road geometry, clearances, traffic management, lifting, and site access. Those requirements can influence a project schedule months before energisation and are one reason high-voltage equipment delivery has to be integrated closely with civil construction.
Manufacture in Chongqing also reflects the international supply chains supporting network expansion. Demand for transformers, reactors, switchgear, and other high-voltage equipment has increased as utilities replace ageing systems, connect new generation, and reinforce networks for electrification and large industrial loads.
Factory capacity can therefore become part of the critical path. A transmission line may have towers, conductors, and substation civil works progressing on site while delivery dates for specialised electrical equipment determine when testing and energisation can actually begin.
HumeLink’s role in connecting new generation and storage makes that sequencing particularly important. Renewable projects can only contribute fully once sufficient network capacity exists to move their output, while a transmission asset cannot enter service until protection, voltage control, switching, and reactive-power equipment are ready.
Long circuits also behave differently under high and low load. During heavy transfer, operators may need voltage support in one direction, while lightly loaded conditions can create excessive reactive power and voltage rise. Shunt reactors provide a controllable means of absorbing that reactive power as system conditions change.
The 500kV rating places the equipment directly in the transmission layer rather than at distribution level. Equipment clearances, insulation coordination, switching duties, protection design, and testing requirements all reflect the energy and fault levels associated with that voltage class.
Final commissioning of the reactors is expected by the end of 2026. Before then, Hitachi Energy and its subcontractors must complete the on-site work needed to transition each unit from transported equipment into an operational network component.
Six reactors weighing more than 720 tonnes in aggregate have now reached HumeLink’s substations. The remaining programme is electrical: connecting, testing, and commissioning them so that a 365km transmission loop can operate within its required voltage and reactive-power limits.


