IN Brief:
- Rezolv Energy has selected 45 Vestas V162-6.5 MW EnVentus turbines for its Dunarea East development in southeastern Romania.
- The procurement follows financial close on a funding package worth up to €367 million, involving six lenders.
- Vestas' responsibilities extend from equipment supply and commissioning to a 15-year Active Output Management service agreement.
Danish wind turbine manufacturer Vestas has secured a contract to supply 45 turbines for Rezolv Energy’s Dunarea East wind farm in southeastern Romania, establishing the equipment specification and associated servicing arrangements for the 292.5 MW generating development.
The agreement covers V162 EnVentus turbines rated at 6.5 MW each, alongside installation, commissioning, and a 15-year Active Output Management service programme. Construction was scheduled to begin before the end of November, with turbine deliveries expected from late 2027 and commercial operation targeted for early 2029.
Located in Constanța County, Dunarea East represents a further collaboration between Vestas and Rezolv following the development of the 461 MW VIFOR wind farm. An initial 192 MW phase of VIFOR, incorporating 30 turbines from the same EnVentus platform, entered commercial operation in October.
Rezolv secured up to €367 million in project financing for Dunarea East earlier in November. Six lenders participated in the transaction, with additional support from Denmark’s Export and Investment Fund.
The involvement of the Danish export finance institution accompanies the procurement of generating equipment from Vestas. Establishing the turbine supply agreement following financial close allows the principal equipment manufacturing and delivery programme to be coordinated with the project’s construction timetable.
The turbines have rotor diameters of 162 metres, giving each machine a swept area of approximately 20,600 square metres. Across the 45-machine fleet, the combined swept area approaches 930,000 square metres.
The generating performance associated with those dimensions will depend on local wind conditions and the behaviour of individual turbines. Extracting energy from the wind changes the velocity and turbulence of the air passing through a rotor, potentially affecting downstream machines.
Wind farm layouts must account for those wake interactions alongside land availability, environmental restrictions, foundation requirements, and access arrangements. Turbine spacing can influence both electricity production and the mechanical loading experienced by equipment over its operating life.
The selection of a specific turbine model also establishes the mechanical and electrical interfaces around which other elements of the development can be designed. Foundation engineering must accommodate the loads imposed by the tower and generating equipment, while the collection network must be capable of carrying the output of the installed machines.
Individual generating units will require electrical protection, control, and communications arrangements coordinated through the wider wind farm infrastructure. The collection circuits must aggregate their output and deliver it through the project’s transmission connection.
Construction schedules must consequently coordinate the completion of turbine foundations, access infrastructure, electrical installation, and the delivery of major turbine components. Progress in one area cannot necessarily compensate for delays elsewhere, particularly where equipment installation depends on the availability of completed supporting structures or electrical circuits.
Commissioning will establish the performance of individual turbines and the combined generating installation. Grid connection requirements can include demonstration of active power control, reactive power capability, and the behaviour of the generating equipment during disturbances in the electricity network.
Vestas’ 15-year service agreement extends its involvement beyond completion of the construction programme. Its Active Output Management arrangements are designed to support electricity production through the maintenance and operation of the generating fleet.
Maintaining generating availability requires coordination of planned maintenance and corrective interventions. Remote monitoring can help identify changes in equipment behaviour before failures occur, while local servicing capacity and spare parts availability influence how quickly an unavailable turbine can return to operation.
Deploying related turbine platforms at both VIFOR and Dunarea East provides an opportunity to build on experience with the earlier installation. The extent to which maintenance resources or spare parts can be shared will depend on the operating and contractual arrangements established across the two projects.
Dunarea East’s revenues are supported by a contract for difference awarded through Romania’s second renewable electricity auction in 2025, covering approximately 211 MW of generating capacity.
Rezolv also has a ten-year virtual power purchase agreement with international food retailer Ahold Delhaize, covering electricity production from Dunarea East and the company’s Dama Solar development.
These arrangements provide longer-term revenue visibility, while the amount of electricity available for sale remains dependent on wind resource conditions, equipment availability, and the capacity of the surrounding electricity network.
The turbine contract establishes the equipment procurement programme through which Dunarea East will progress from its recently completed financing transaction towards construction and commissioning. Vestas will subsequently remain involved in servicing the installation throughout the initial 15 years of its contracted maintenance programme.