IN Brief:
- Framatome has converted approximately 15,000 square metres of industrial premises and created around 50 jobs.
- The six planned EPR2 reactors will require more than 45,000 individual reactor internals parts.
- Manufacturing began in July 2026, with first deliveries scheduled for 2032.
Nuclear engineering company Framatome has inaugurated a manufacturing and assembly workshop at Le Creusot in eastern France, following an investment approaching €100 million to expand domestic production of reactor pressure vessel internals for the country’s planned EPR2 nuclear power fleet.
The development involved acquiring and converting approximately 15,000 square metres of industrial space and installing large machining, welding, and assembly equipment. Around 50 jobs have been created. French minister delegate for industry Sébastien Martin and EDF chairman and chief executive Bernard Fontana attended the inauguration on 24 November.
Production began in July as part of preparations for six EPR2 reactors, with the first deliveries of internals scheduled to commence in 2032. Framatome expects the six sets required by the programme to contain more than 45,000 individual parts, creating a substantial series manufacturing requirement for the site.
Reactor pressure vessel internals maintain the position of the fuel assemblies and provide structures that guide coolant through the core. In a pressurised water reactor, primary coolant transfers heat from the core to steam generators, where that energy is transferred to a separate secondary circuit. The steam produced in the secondary circuit subsequently drives the generating turbine.
The internals consequently perform a different function from the pressure vessel itself. While the vessel retains the primary coolant under pressure, internal structures must support the core and maintain the required geometry for coolant circulation and fuel positioning. Mechanical loads, thermal expansion, and the conditions encountered during reactor operation must all be accounted for in component design and manufacturing.
Producing structures assembled from thousands of individual parts requires coordination between material procurement, machining, welding, examination, and assembly. Dimensional tolerances established at the machining stage must remain achievable after welding and assembly, since deviations in individual parts can affect the geometry of the completed structure.
Welding introduces local heating and cooling that can cause distortion and residual stresses. Managing these effects requires appropriate procedures and inspection during manufacture. Qualified manufacturing processes and documented material provenance are also essential to demonstrating that the delivered assembly satisfies its design and applicable nuclear quality requirements.
The new workshop provides dedicated space for these activities alongside Framatome’s existing heavy manufacturing infrastructure at Le Creusot. The wider site employs more than 680 people and produces components including forgings for nuclear steam supply systems and sections of primary coolant pipework. Its manufacturing capabilities span the preparation of forged parts through to the assembly of reactor internals.
Framatome has also incorporated two training areas into the new workshop, focusing on machining and welding. Locating training alongside production allows the workforce to develop competence with relevant equipment and procedures as the company increases output. The demand for repeatable manufacturing quality across six reactor sets requires both sufficient personnel and continuity of specialist knowledge throughout the delivery programme.
The premises use geothermal energy to manage workshop temperatures, reducing reliance on conventional heating and cooling equipment. Stable manufacturing conditions can also support dimensional measurement of large metal components, since their dimensions vary with temperature. Framatome has not specified the geothermal installation’s capacity or quantified its energy savings.
The investment sits within a broader programme of manufacturing preparations for EPR2. Framatome’s project plans cover six reactor pressure vessels as well as other major components of the nuclear steam supply system. The company has already documented preparatory work at Le Creusot involving an ingot for the first EPR2 unit’s primary circuit pipework, received in February 2025.
The relationship between component manufacturing and site construction extends well beyond the date at which a reactor begins generating electricity. Large nuclear components must be procured, qualified, and produced in advance of the installation sequence, often using dedicated machinery that cannot readily be transferred between suppliers. A delayed manufacturing package can therefore affect downstream construction activities even where the building works are progressing to schedule.
France’s programme creates an opportunity to repeat production across several reactor units rather than establish a complete manufacturing arrangement for each individual project. Repetition can allow manufacturing procedures, tooling, and workforce experience to be carried forward, provided the equipment design and qualification requirements remain compatible. It does not remove the need to inspect and document each delivered component.
Framatome’s investment in Le Creusot follows other recent expansions of its nuclear supply chain, including the separate €30 million nuclear fuel coating facility. The reactor internals workshop addresses a different manufacturing requirement, associated with the structures inside the reactor vessel rather than the fabrication of fuel itself.
The first EPR2 internals deliveries remain scheduled for 2032. Between the start of series production this year and those deliveries, Framatome must establish the required production throughput and demonstrate consistent manufacturing quality across successive assemblies.