Welsh solar and battery projects receive funding

Welsh solar and battery projects receive funding

Two Welsh solar and storage projects have secured capital grants. The Pembroke Dock and Carmarthen schemes combine photovoltaic generation with battery systems, with the latter also incorporating a heat pump.


IN Brief:

  • Ynni Cymru has awarded £997,566 to Renewable Power Pembrokeshire and £233,032 to Carmarthenshire Energy for local generation and storage schemes.
  • The proposed installations comprise 750kW solar with 400kW battery power in Pembroke Dock and 200kW rooftop solar with 75kW battery power at Xcel Bowl.
  • The Welsh Government listed the awards on 19 October, and the regional committee published the two project specifications on 29 October.

South West Wales Corporate Joint Committee has detailed two community electricity schemes in Pembrokeshire and Carmarthenshire that combine solar generation with battery storage. Renewable Power Pembrokeshire has secured a maximum Ynni Cymru capital grant of £997,566 for a proposed Pembroke Dock installation, while Carmarthenshire Energy Ltd has been allocated up to £233,032 for equipment at Xcel Bowl in Carmarthen. The committee’s project descriptions give the generating and storage power ratings behind grants first listed by the Welsh Government in October.

The allocations fall within the 2026–27 Ynni Cymru funding programme, and the published amounts represent maximum awards that can change as formal grant letters are agreed. The funding supports local energy systems developed by community organisations, businesses, and public bodies. At both sites, the announced equipment remains a project specification rather than a completed installation: detailed design, procurement, construction, electrical connection, and commissioning must follow before generation and storage can enter service.

Renewable Power Pembrokeshire’s scheme comprises 750kW of solar photovoltaic capacity alongside a battery system rated at 400kW. Both figures describe power: the solar rating indicates generation capacity, and the battery figure indicates its stated charge or discharge power. Battery duration cannot be calculated without an energy rating in kilowatt-hours or megawatt-hours. The storage specification will determine how much solar production can be shifted between periods of generation and use, in combination with the local electrical demand.

Photovoltaic modules generate direct-current electricity, which power electronics convert into alternating current for buildings or the distribution network. Their output varies with the available solar resource, while a battery can absorb electricity during suitable charging periods and deliver it later. In a combined system, inverters, protection equipment, and the site controller must coordinate those movements while respecting the connection’s import and export limits. The proposed battery’s 400kW power rating sets one electrical boundary; its usable stored energy and operating schedule will set others.

Electrical connection arrangements will determine whether each installation primarily supplies local buildings, exports electricity, or operates through a combination of on-site consumption and export. A battery discharge cannot exceed the available stored energy, even when its instantaneous power equipment is capable of operating at the stated rating. Equally, solar electricity that cannot be consumed, exported, or stored at a particular moment must be managed within the installation’s operating limits. Metering and system control will establish how those constraints are handled in practice.

The Pembroke Dock scheme is the first project to emerge from the region’s Innovate UK-funded Industrial Decarbonisation Powered by Communities Launchpad. The programme brought local authorities, businesses, and community partners together to develop projects linking locally generated and stored electricity with demand in the area. That development work preceded the Ynni Cymru allocation and provides a route for the participating organisations to turn the project concept into engineering and delivery requirements.

At Xcel Bowl in Carmarthen, the Ynni Sir Gâr project has a different equipment mix: 200kW of rooftop solar capacity, a battery rated at 75kW, and a heat pump. The rooftop location brings the generating equipment into the building’s electrical system, requiring the solar connection, protection, and metering to be coordinated with existing loads. The battery provides an additional controllable electrical interface, with its dispatch governed by its eventual energy capacity and the site’s operating arrangements.

The heat pump adds electrical demand associated with supplying heat to the building. Heat-pump equipment uses electrical input to move thermal energy from a source to a useful temperature, allowing it to deliver heat through a thermodynamic cycle. Its electricity consumption will vary with the heating requirement, selected equipment, and temperature conditions. The proposed solar and battery equipment could supply some of that demand when generation or stored energy is available, subject to the building’s heating schedule and the controls chosen for the installation.

The two sites therefore have different electrical operating requirements. Pembroke Dock’s proposed generating and battery power ratings are larger, while the Carmarthen installation places storage alongside rooftop generation and a heat-pump load. Network connection studies, protection settings, equipment sizing, and commissioning tests will need to reflect those specific arrangements. Their battery power figures establish the conversion limits, while energy capacity and operating arrangements will determine the amount of electricity available over time.

The Welsh Government’s latest Ynni Cymru round covers 24 organisations across Wales, with maximum awards totalling approximately £8.27m. Seven recipients in Pembrokeshire, Carmarthenshire, and Ceredigion account for around £2.75m of that sum. Across the programme, investment since its 2023 launch now exceeds £31m, supporting organisations that want to develop and use locally generated clean electricity. The west Wales projects sit within that broader group of community and public-benefit installations.

South West Wales Corporate Joint Committee is working with local authorities, community energy organisations, and project partners on the transition towards delivery. The Pembroke Dock Launchpad work has already established a collaboration around local demand, while the Carmarthen scheme will need to coordinate electrical generation and heating at its named building. The next site-specific evidence will come from procurement, installation, connection approval, and acceptance testing against the final specifications.

Once commissioned, generation meters, battery operating records, and building electricity consumption will show how the two systems actually perform. The projects have identified their planned generating power, storage power, sites, and capital support; their energy capacity, operating schedules, and completed electrical connections will determine how local electricity is used and stored.


  • ABB introduces AI-assisted control room software

    ABB introduces AI-assisted control room software

    ABB has launched software combining anomaly detection with process simulations. Augmented Operator retrieves historic plant events and forecasts changes, while control room personnel retain authority over operational decisions.


  • METEC wins offshore substation corrosion protection contracts

    METEC wins offshore substation corrosion protection contracts

    METEC has secured four contracts for marine corrosion protection systems. Two cover offshore wind substation jackets in France and the Netherlands, with other anode supplies destined for port infrastructure.