IN Brief:
- Ember, Energy Square, and Cleantech for Italy estimate that renewable electricity shifted through battery storage could cost between €106 and €122/MWh.
- The research compares those estimates with an average gas-fired generation cost of €210/MWh under October 2026 fuel-price conditions.
- Italy's second MACSE auction awarded 16 GWh of electricity storage capacity for delivery in 2029.
Research from energy think tank Ember, Energy Square, and Cleantech for Italy estimates that electricity generated by wind and solar installations and subsequently discharged from battery storage could cost up to 49% less than conventional gas-fired generation in Italy.
The analysis, published on 26 November, estimates an average cost of between €106 and €122/MWh for renewable electricity shifted through batteries, depending on when the storage installations are charged. Electricity production from a typical Italian gas-fired power station averaged an estimated €210/MWh under October’s gas-price conditions.
The findings follow Italy’s second procurement auction under its Electricity Storage Capacity Procurement Mechanism (MACSE), through which transmission system operator Terna awarded contracts covering 16 GWh of storage capacity for delivery in 2029.
The auction attracted bids approaching three times the required capacity, with successful projects securing annual remuneration for the storage capability they make available.
Terna allocated approximately 9.6 GWh to southern Italy and Calabria, 3 GWh to Sicily, 2.8 GWh to central-southern Italy, and approximately 500 MWh to Sardinia. The geographical distribution reflects the storage requirements associated with integrating additional renewable generation across different parts of the electricity network.
Under MACSE, developers compete for long-term payments based on contracted energy storage capacity. Market participants can subsequently access the storage services provided through those assets, creating opportunities to shift electricity delivery without necessarily owning the underlying installations.
Ember’s analysis incorporates the costs associated with procuring renewable electricity and subsequently storing it. The resulting estimate depends on the charging conditions because electricity prices can differ substantially between periods of abundant renewable generation and those in which gas-fired power stations remain necessary to meet demand.
The annual remuneration awarded through MACSE should not be confused with the cost of each megawatt-hour subsequently discharged. The former establishes a payment for making storage capacity available, while the latter depends on how frequently the equipment is operated and the quantity of electricity delivered over its lifetime.
A storage installation cycled regularly can distribute its fixed costs across a larger quantity of discharged electricity than an equivalent asset operated infrequently. However, intensive cycling can also accelerate battery degradation, potentially increasing maintenance and replacement requirements.
Conversion losses further influence the cost of delivered electricity. A battery must consume more energy during charging than it subsequently returns to the network, with the difference reflecting losses within the cells, power conversion equipment, and associated electrical infrastructure.
Italy’s expanding photovoltaic generating fleet creates opportunities to obtain electricity during periods when solar production depresses wholesale prices. As photovoltaic output declines towards the evening, gas-fired generation can become increasingly important in meeting electricity demand.
Shifting a portion of that daytime generation into evening periods can reduce the amount of electricity that must be produced by gas-fired power stations. The achievable substitution depends on the storage capacity available and the duration of the period during which additional electricity is required.
Batteries providing several hours of discharge can address relatively predictable daily variations in photovoltaic generation. Longer periods of low renewable output require sufficient opportunities to recharge those installations or alternative sources of electricity capable of sustaining production.
The regional allocation of MACSE capacity also affects its potential contribution to network operation. Renewable generation in southern Italy and its islands must be accommodated within the transmission infrastructure connecting those areas with demand elsewhere in the country.
Charging storage installations during periods when renewable generation exceeds local demand can reduce the amount of electricity that must be transferred through constrained transmission corridors. Subsequent discharge must nevertheless be coordinated with network conditions to avoid recreating the restrictions the storage was intended to alleviate.
The research also suggests that reductions in electricity market expenditure could offset the cost to consumers of remunerating contracted MACSE storage capacity. Such an outcome would depend on how the installations are operated, the volume of gas-fired production they displace, and the resulting changes in wholesale electricity prices.
The comparison between stored renewable electricity and gas generation is particularly sensitive to fuel prices. Lower gas prices would narrow the estimated cost differential, while higher fuel or carbon costs could strengthen the relative economics of renewable electricity storage.
Italy’s latest auction establishes the commercial basis for a substantial expansion in storage infrastructure. With the contracted installations scheduled to enter operation in 2029, their actual utilisation, efficiency, and effect on electricity market prices will determine whether the savings identified in the research can be achieved.