IN Brief:
- The Trongstadlia hydropower development has entered operation in Åfjord municipality, central Norway.
- Its hydraulic infrastructure incorporates a 46-metre gross head and an approximately 1.2 km waterway.
- A new electricity line constructed with distribution network operator Tensio has extended grid access into the surrounding community.
Nordic renewable infrastructure developer Locus Energy has completed its 5 MW Trongstadlia hydropower development in central Norway, adding an anticipated 13.4 GWh of annual electricity production to the country’s NO3 electricity bidding area.
Located on the Amundalselva river in Åfjord municipality, Trøndelag, the installation was commissioned in October, with Locus Energy confirming completion of the development on 26 November.
Trongstadlia formed part of a portfolio of small-scale Norwegian hydropower projects acquired from Blåfall Utvikling in May 2024. Locus Energy subsequently undertook the detailed engineering, procurement, and construction required to bring the generating asset into operation.
Water is conveyed between an intake situated 201 metres above sea level and a powerhouse at 155 metres, providing a gross hydraulic head of 46 metres. The installation’s waterway extends approximately 1.2 km, with its generating equipment designed to accommodate a maximum flow of 12.6 cubic metres per second.
The relationship between hydraulic head and water flow determines the amount of energy potentially available for electricity generation. At the stated gross head and maximum flow, the water would carry approximately 5.7 MW of hydraulic power before accounting for losses.
The plant’s 5 MW electrical rating reflects the conversion of that hydraulic energy into electricity, although calculating its precise efficiency would require additional information concerning the net head available at the turbine and the operating characteristics of the generating equipment.
The difference between gross and net head is particularly relevant where water must travel a substantial distance before reaching the powerhouse. Friction along the waterway and losses associated with changes in its geometry reduce the pressure available to the turbine.
Those losses generally increase as the volume of water passing through the infrastructure rises. Hydraulic design must therefore balance the expenditure associated with constructing a larger waterway against the potential improvement in generating performance over the plant’s operating life.
At Trongstadlia, approximately 1,030 metres of the waterway have been constructed through rock beneath the Trongstadlia Nature Reserve. Routing the infrastructure underground allowed construction to avoid disturbing the protected coastal spruce forest above it.
The developer also revised the proposed intake during detailed engineering, obtaining approval from Norway’s Water Resources and Energy Directorate in February 2025 to replace the original conventional design with a Tyrolean intake.
The alternative design uses a lower, wider weir, addressing requirements concerning upstream flood levels while reducing the potential accumulation of sediment at the intake.
A Tyrolean intake generally collects water through a screen positioned within the flow path. Its design can allow some sediment and debris to continue downstream rather than entering the generating infrastructure.
Managing that material affects both the hydraulic performance of the installation and its maintenance requirements. Abrasive particles carried through a turbine can contribute to wear, while debris accumulating around an intake can restrict the amount of water available for generation.
The operating concession requires a residual river flow of at least 390 litres per second throughout the year. This reduces the quantity available for diversion through the generating installation, particularly during periods of comparatively low river flow.
Consequently, Trongstadlia’s electrical output will vary according to precipitation, seasonal water availability, and the operating limits established for the development.
Its forecast annual production of 13.4 GWh corresponds to approximately 2,680 equivalent full-load generating hours, representing an indicative capacity factor of around 31%. A significant proportion of production is expected during the winter, when regional electricity consumption is typically higher.
Construction involved several Norwegian contractors, including Energi Teknikk for the electromechanical equipment. The installation of that equipment had to be coordinated with the completion of the hydraulic infrastructure and arrangements for connection to Tensio’s distribution network.
The availability of electrical protection and control systems is central to the transition from completed construction to operational generation. Hydropower facilities must coordinate the flow of water through the turbine with the electrical output delivered by the generator, responding appropriately when generating or network conditions change.
Specialist investment in those control arrangements is also taking place at existing Nordic installations. Finnish engineering group Valmet recently secured a contract to modernise automation and electrical protection at three hydropower plants operated by Kainuun Voima.
Trongstadlia’s connection programme included the construction of a new high-voltage line through Sørdalen, extending electricity supply to an area previously without grid access. Associated infrastructure has also enabled fibre broadband provision.
The completed generating facility adds to Locus Energy’s existing Norwegian hydropower portfolio, with its output supporting the regional electricity supply through Tensio’s distribution network. Its actual annual production will be determined by river conditions and equipment availability over successive operating seasons.