energyRe secures $815m for South Carolina solar projects

energyRe secures 5m for South Carolina solar projects

energyRe has closed major financing for five South Carolina projects. The $815m package supports approximately 360MW of solar generation backed by 25-year electricity purchase agreements, although the company has not named the individual projects in the latest release.


IN Brief:

  • energyRe has closed an $815m financing package for five South Carolina solar developments with approximately 360MW of combined capacity.
  • Bank of America, CIBC and Santander supported the transaction, which is backed by 25-year power purchase agreements.
  • The closing takes energyRe's reported financing for its wider solar portfolio above $1.9bn.

US renewable energy developer energyRe has closed an $815m financing package for five utility-scale solar developments in South Carolina, securing capital for approximately 360MW of additional generating capacity. The projects are backed by 25-year power purchase agreements, providing long-term electricity sales arrangements as the company advances its construction and investment programme.

The transaction, announced on 12 October, was supported by Bank of America, Canadian Imperial Bank of Commerce (CIBC) and Santander. Bank of America acted as documentation agent and Santander served as financial adviser, while energyRe’s mergers and acquisitions and capital markets team coordinated the financing with its lending and tax equity partners.

energyRe describes the agreement as its largest portfolio financing to date and one of South Carolina’s largest transactions involving solar generation alone. The developer has not published a breakdown of the $815m package by financing instrument, nor has it identified the precise amount attributable to individual projects.

The company previously announced 25-year electricity purchase agreements for five South Carolina projects totalling 360MW in February. Those developments were named as Shorthorn Solar, Culpepper Solar, Clarendon Solar, Rollins Solar and Ross Solar. Although the capacity and commercial arrangements match the October financing announcement, energyRe has not explicitly identified the five financed developments in the latest release, so the earlier project list cannot yet be treated as confirmed for this transaction.

The financing follows the establishment of the projects’ contractual arrangements for selling electricity. A power purchase agreement specifies how electricity will be bought and sold once a generating facility becomes operational, while project financing provides capital for development and construction under terms that reflect expected costs, revenues and associated risks.

Long-term electricity sales agreements can reduce uncertainty for lenders, but they do not remove the engineering and delivery requirements that determine when a project begins earning revenue. Solar installations must complete construction, establish their electrical connections and satisfy commissioning requirements before commercial generation can begin.

A utility-scale photovoltaic development includes more than the generating modules installed across its site. Direct-current collection circuits carry electricity to power conversion equipment, where inverters produce alternating current suitable for transmission through transformers and switchgear. The resulting electricity is exported through the connection established with the relevant network operator.

Equipment selection and electrical design must reflect the generating station’s permitted export capacity and the operating requirements at its connection point. Inverters need to regulate their output within specified limits, while transformers, cables and protection equipment must be rated for the electrical conditions expected during normal operation and faults.

Construction schedules also depend on the availability of the grid connection. A solar array may be mechanically complete before the associated substation or network reinforcement is ready, leaving further electrical work and testing necessary before export can begin. Financing arrangements consequently have to accommodate expenditure incurred before the generating assets reach commercial operation.

The five-project portfolio provides opportunities to spread development and delivery risks across several installations, although each remains subject to its own site conditions and construction requirements. The October announcement does not identify the photovoltaic module manufacturers, inverter suppliers, connection voltages or expected completion dates for the individual projects.

Annual production from the portfolio will depend on sunlight, equipment availability and the amount of energy that can be exported through the completed electrical connections. The combined 360MW rating describes installed generating capacity rather than continuous output, and the projects’ actual contribution to the electricity system will vary throughout the day.

Pedro Pereira, Chief Financial Officer of energyRe, described the agreement as the company’s largest portfolio financing transaction. He said it reflected lenders’ confidence in the assets and the company’s ability to deliver them, with the closing advancing energyRe’s ambition to invest $2bn in South Carolina by 2030.

The company expects the financed developments to generate employment during construction and operation, alongside tax revenues for local communities over their working lives. The announcement forecasts revenue for local governments amounting to tens of millions of dollars, although it does not provide a breakdown by project or local authority.

energyRe has broken ground on approximately 450MW of solar capacity during the past year and reports that nearly 700MW is either operational or at an advanced stage of development. Its wider solar portfolio exceeds 1.8GW across 20 projects in South Carolina, North Carolina, Nebraska and Oklahoma.

These portfolio figures describe projects at different stages and should not be added together as though they represent separate blocks of newly commissioned capacity. The developer’s October announcement does not establish that the five financed South Carolina projects are already generating electricity.

The latest agreement brings total financing raised for energyRe’s solar portfolio to more than $1.9bn. An earlier $370m South Carolina financing transaction was announced in October 2025, but energyRe has not supplied sufficient project-level information in the latest release to establish how each historical financing package relates to every development in the current portfolio.

The financial closing gives the five projects a firmer capital basis for their remaining delivery activities. Their next measurable milestones will be completion of the generating and connection infrastructure, electrical testing and the commencement of commercial operation under the existing electricity purchase agreements.